Septic-to-Sewer Program — Indian River County, Florida

The county utility is converting lagoon-side neighborhoods from North Sebastian to Hobart Landing, while Vero Beach runs its own STEP program with a 2028 date.


Short answer: As of October 12, 2026, the Indian River County Department of Utility Services lists four septic-to-sewer projects: Floravon Shores Phase 2 (19 homes, bidding), North Sebastian Phase 3 (168 homes, design), Hobart Landing (about 53 homes, 75% FDEP-funded) and Wabasso Island (procurement), plus FDEP-funded aid of up to $15,000 per eligible property. Under Florida law, owners must connect within 365 days of a written notice that sewer is available. Vero Beach runs a separate STEP program with a June 1, 2028 deadline.

Last verified: October 12, 2026, against the sources listed at the end of this page.

Which septic-to-sewer projects is Indian River County running in 2026?

As of October 12, 2026, the Indian River County Department of Utility Services lists four neighborhood conversions, at Floravon Shores, North Sebastian, Wabasso Island and Hobart Landing, plus a countywide Sewer Connection Assistance Program.

Each job carries a utility project number and a phase from a seven-step scale that runs from procurement through design, permitting, bidding, construction and closeout to complete (county Septic-to-Sewer Program). Floravon Shores Phase 2, project 21.19.556 on 110th Street, is the furthest along: 19 homes close to the lagoon shore, a community meeting on March 31, 2026, and construction bids open through contractor award.

The largest neighborhood job is North Sebastian Phase 3, project 21.26.505, which takes in 168 homes on streets around North Sebastian, with engineering and design underway (Indian River County Septic-to-Sewer page). Hobart Landing, project 21.24.508, is smaller at approximately 53 homes, and the county says three quarters of its cost comes from the state. The Wabasso Island job, project 41.24.507, pairs septic removal with utility improvements and was still soliciting qualifications for an engineering firm or design-build team.

Indian River County Septic-to-Sewer Program projects (IRCDUS program site, fetched October 12, 2026)
ProjectIRCDUS project IDSizePhase
Floravon Shores Phase 2 (110th Street)21.19.55619 homesBid
North Sebastian Phase 321.26.505168 homesDesign
Hobart Landing21.24.508About 53 homesDesign (field investigation)
Wabasso Island41.24.507Not yet statedProcurement
Sewer Connection Assistance Program (North, Central and South zones)21.26.520Up to $15,000 per eligible propertyProcurement

Who provides sewer in Sebastian, Fellsmere, Vero Beach and the unincorporated county?

The Indian River County Department of Utility Services serves the unincorporated county, runs the conversions in North Sebastian and treats Fellsmere's wastewater in bulk, while the City of Vero Beach runs its own system with its own conversion rules.

The county utility's reach is large. Its collection system takes wastewater from approximately 34,000 retail service connections in unincorporated Indian River County, and the same Department of Utility Services provides bulk sewer treatment service to the City of Fellsmere (IRCDUS rate study, page 5). That flow goes to four active wastewater treatment facilities with a combined permitted treatment capacity of 12.02 MGD. On the water side, the utility serves about 56,000 retail customers (IRCDUS rate study site).

Vero Beach is the exception inside the county. The city converts homes with a septic tank effluent pump, or STEP, system and its Ordinance No. 2024-05 requires connection to a central sewer system by June 1, 2028 or within one year of the sale, conveyance or transfer of a property served by septic (City of Vero Beach Ordinance 2024-05). The council chose the earlier date to allow for a more organized transition from a septic system to a STEP System, and to help residents who cannot connect before the state deadline of July 1, 2030.

Enforcement in Vero Beach runs through city code. After June 1, 2028, or a year after a sale, an owner who has not connected is in violation, and the utility director notifies the city's Code Enforcement Officer (Ordinance 2024-05, page 3). Septic owners outside Vero Beach, in places such as North Sebastian, Wabasso Island or Floravon Shores, deal with the county program instead.

How is the county's septic-to-sewer work paid for?

Indian River County pays for conversions through its utility enterprise fund, which runs on customer rates rather than taxes, topped up by Florida Department of Environmental Protection grants for jobs such as Hobart Landing.

Indian River County Utilities states that its operations and capital improvements are funded exclusively through user fees (not through taxes), and that rate increases took effect January 1, 2025 with a second on October 1, 2025 (IRCDUS rate study site). The consultant's financial plan behind those increases set the sewer rate plan at 24.00% for FY 2025 and 12.00% for FY 2026 (IRCDUS rate study, page 60). The same plan assumes an additional 100 Septic to Sewer (S2S) connections per year when it projects revenue (IRCDUS rate study, page 49).

Grant money lowers the cost to owners on specific jobs. A state FDEP grant covers 75% of Hobart Landing, and the Sewer Connection Assistance Program will pay eligible owners up to $15,000 each, from FDEP grant money, to hook up where a county line already runs past the lot in the utility's north, central or south service areas (Indian River County Septic-to-Sewer page). On October 12, 2026 the county was still introducing that program ahead of the application portal opening.

The capital plan shows where the large dollars sit. The Sebastian Highlands carry three septic-to-sewer lines in the FY 2024 to FY 2034 Capital Improvement Program, with Unit 05 the largest at $22,670,872 (IRCDUS rate study, page 58). Orchid Island No.2 is budgeted at $9,900,000 and Hobart Landing Unit 2 at $4,400,000, while smaller lines cover North Sebastian Phase 2, Floravon Shores and West Wabasso Phase 3A. Septic work competes in that schedule with other utility jobs, such as $1,829,521 for the North County 24-inch force main replacement and $5,193,994 for Oslo water treatment plant improvements, both in FY 2024.

Who sets the rates matters for every customer on the county system, from Wabasso to the South County service area. The Board of County Commissioners has periodically conducted formal rate studies, and the one before the FY 2024 study was completed in 2018 (IRCDUS rate study, page 5). The utility's own comparison puts its FY 2024 residential water and sewer charges the lowest of 14 peer utilities, with the highest more than twice as much (IRCDUS rate study site).

Septic-to-sewer lines in the IRCDUS FY 2024 Capital Improvement Program, total cost (Stantec rate study, page 58)
Capital lineTotal cost
S2S, Sebastian Highlands Unit 05$22,670,872
S2S, Sebastian Highlands Unit 04$11,452,041
S2S, Orchid Island No.2$9,900,000
S2S, Hobart Landing Unit 2$4,400,000
S2S, Sebastian Highlands Unit 02 Collier$2,165,998
S2S, West Wabasso Phase 3A, Public$1,012,527
S2S, Floravon Shores, Public$642,375
S2S, North Sebastian Phase 2, Private$325,412

What must an owner do once county sewer becomes available?

Under section 381.00655 of the Florida Statutes, an owner whose septic system works properly must connect to an available public sewer, such as an Indian River County Utilities line, within 365 days of the utility's written notice.

The statute builds in warning time. A public utility must tell the owner no less than 1 year before the sewer line will become available that the connection will be required within 1 year of actual availability (Section 381.00655, Florida Statutes). For a North Sebastian, Hobart Landing or Wabasso Island owner, that means two notices: one at least a year before the line becomes available, and the availability notice that starts the 365 days.

Payment can be spread out, including for an Indian River County Utilities connection. The same section gives the owner the option of prepaying the amortized value of required connection charges in equal monthly installments over a period not to exceed 2 years from the initial notice of anticipated availability (Section 381.00655).

A failing tank moves faster. When a septic system needs repair to function in a sanitary manner, its owner must connect to an available public sewer within 90 days after written notification from the department, and in hardship cases one extension of not more than 90 days may be approved (Section 381.00655). That rule applies equally in Fellsmere, Sebastian and the unincorporated county wherever a line runs past the property.

What does the July 1, 2030 lagoon deadline mean for county septic owners?

By July 1, 2030, Florida's lagoon law requires septic properties in its plan areas, including the Central Indian River Lagoon basin plan that Vero Beach Ordinance 2024-05 cites, to connect to available sewer or cut nitrogen by at least 65 percent.

Section 373.469, the Indian River Lagoon Protection Program, reaches every commercial lot, and every home lot of 10 acres or less, still on septic inside four plan areas: the Banana River, Central Indian River Lagoon and North Indian River Lagoon basin plans and the Mosquito Lagoon plan (Section 373.469, Florida Statutes). New septic systems have been prohibited in those areas since January 1, 2024 where a public sewer is available.

Where no Indian River County Utilities line reaches the lot, the route is an upgrade rather than a hookup. The statute authorizes only enhanced nutrient-reducing onsite systems, or other treatment systems that achieve at least 65 percent nitrogen reduction, in places where central sewer is not available (Section 373.469). Before July 1, 2030, any agency handling an application to repair or replace a conventional system must tell the owner about the deadline.

The county's own sequencing follows the lagoon. Its program site says the county has prioritized neighborhoods closest to the Indian River Lagoon and its tributaries, where septic systems have the most direct impact on water quality (county Septic-to-Sewer Program). Questions about a specific street in North Sebastian, Floravon Shores or Hobart Landing go to projectinfo@IRCS2SProgram.com. Last verified: October 12, 2026, on the Indian River County website.

Frequently asked questions

Is the Sewer Connection Assistance Program taking applications?

Not as of October 12, 2026. The county program site lists it as project 21.26.520 and says the county is still explaining funding options and connection rules before an application portal opens. Eligible owners in the North, Central and South service zones will be able to get up to $15,000 per property from an FDEP grant.

Does Fellsmere have its own sewer treatment plant?

The Indian River County Department of Utility Services provides bulk sewer treatment service to the City of Fellsmere, according to the utility's FY 2024 rate study, so Fellsmere wastewater is treated at county facilities.

Why does Vero Beach have an earlier deadline than the rest of Indian River County?

Vero Beach Ordinance No. 2024-05 set June 1, 2028, or one year after a sale, for connecting to the city's STEP sewer, to allow a more organized transition and to help residents who cannot connect before the state's July 1, 2030 deadline.

Do property taxes pay for county sewer conversions?

No. Indian River County Utilities operates as an enterprise fund, and it states that operations and capital improvements are funded exclusively through user fees, not taxes. State FDEP grants pay part of some projects, such as 75% of Hobart Landing.

How long does a Wabasso or Sebastian Highlands owner have after the sewer letter arrives?

Section 381.00655 of the Florida Statutes gives the owner of a working septic system 365 days after written notice that public sewer is available. A system that needs repair has 90 days after notice from the state department, with one possible 90 day extension.

Sources

  1. Septic-to-Sewer Program, Indian River County Department of Utility Services https://www.ircs2sprogram.com Used for: project list, project IDs, phases, home counts, FDEP grant share, Sewer Connection Assistance Program
  2. Septic to Sewer (S2S), Indian River County Utilities, indianriver.gov https://indianriver.gov/services/utilities/septic_to_sewer_(s2s).php Used for: North Sebastian Phase 3, Wabasso Island and assistance program status on the county government site
  3. FY 2024 IRCDUS Water, Sewer and Reclaimed Water Rate Study (Stantec), page 5 https://img1.wsimg.com/blobby/go/435704ba-e4d0-4fe3-9e6d-833136937b0e/downloads/fy24_ircdus_rate_study_final_report.pdf#page=5 Used for: 34,000 sewer connections, Fellsmere bulk service, four treatment facilities
  4. FY 2024 IRCDUS Rate Study, page 49 (projection of cash inflows) https://img1.wsimg.com/blobby/go/435704ba-e4d0-4fe3-9e6d-833136937b0e/downloads/fy24_ircdus_rate_study_final_report.pdf#page=49 Used for: 100 additional septic-to-sewer connections per year assumption
  5. FY 2024 IRCDUS Rate Study, page 58 (Capital Improvement Program, Schedule 6) https://img1.wsimg.com/blobby/go/435704ba-e4d0-4fe3-9e6d-833136937b0e/downloads/fy24_ircdus_rate_study_final_report.pdf#page=58 Used for: septic-to-sewer capital lines: Sebastian Highlands units 02, 04, 05, Hobart Landing Unit 2, Orchid Island No.2, North Sebastian Phase 2, Floravon Shores, West Wabasso Phase 3A
  6. FY 2024 IRCDUS Rate Study, page 60 (financial plan control panel) https://img1.wsimg.com/blobby/go/435704ba-e4d0-4fe3-9e6d-833136937b0e/downloads/fy24_ircdus_rate_study_final_report.pdf#page=60 Used for: sewer rate plan percentages FY 2025 and FY 2026
  7. Section 381.00655, Florida Statutes: connection of existing septic systems to central sewer https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0300-0399/0381/Sections/0381.00655.html Used for: 365-day connection rule, one-year advance notice, two-year prepayment option, 90 days for failing systems
  8. Section 373.469, Florida Statutes: Indian River Lagoon Protection Program https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0300-0399/0373/Sections/0373.469.html Used for: January 1, 2024 prohibition, July 1, 2030 requirement, 65 percent nitrogen reduction
  9. IRCDUS Comprehensive Rate Study information site https://ircutilityrates.com/home Used for: enterprise fund, rate increase dates, 56,000 water customers, peer comparison
  10. City of Vero Beach Ordinance No. 2024-05, STEP connection by June 1, 2028, page 1 https://www.covb.org/DocumentCenter/View/7561/STEP-Connection-To-A-Central-Sewer-System-By-June-1-2028-Or-Within-1-Year-Of-Sale-Conveyance-Or-Transfer-of-Properties-No-2024-05-PDF#page=1 Used for: Vero Beach earlier deadline and reason
  11. City of Vero Beach Ordinance No. 2024-05, page 3 https://www.covb.org/DocumentCenter/View/7561/STEP-Connection-To-A-Central-Sewer-System-By-June-1-2028-Or-Within-1-Year-Of-Sale-Conveyance-Or-Transfer-of-Properties-No-2024-05-PDF#page=3 Used for: violation after June 1, 2028 or one year after sale
Last updated: October 12, 2026