Undergrounding Tallahassee's Power Lines

Tallahassee builds new subdivisions with buried lines and splits the cost of converting old ones, but most storm money goes to hardening the overhead system under the oaks.


Short answer: The City of Tallahassee owns its electric utility, about 3,600 miles of primary and secondary distribution and more than 64,000 poles. City standard is underground service for all new subdivisions and development. For older areas the city pays 100% of a branch line conversion if customers pay for their delivery point changes, and 25% of a feeder conversion if the requester covers customer delivery and easements.

Last verified: October 18, 2026, against the sources listed at the end of this page.

Why are so many Tallahassee power lines still on poles?

Tallahassee buries lines mainly in new development and in conversions that customers help pay for, not through a citywide program, per the city utility's May 13, 2025 presentation to the Florida Public Service Commission.

That presentation sizes the system: a 221 square mile regulated service territory that includes portions of unincorporated Leon County, more than 124,000 customers, 219 miles of high voltage transmission, 3,600 miles of primary and secondary distribution, more than 28,000 transformers and more than 64,000 poles. The electric utility began commercial operation in 1902. The city's slides do not split the distribution mileage into overhead and underground miles, so this page does not give a split.

Because Tallahassee runs its own system, the decision about what gets buried rests with the City of Tallahassee and its City Commission rather than with a state-regulated company. The city's storm plan pairs that undergrounding policy with tree trimming and pole inspections on the overhead system.

What did Hurricane Hermine and the 2024 storms show about the Tallahassee grid?

Hurricane Hermine showed how exposed the overhead system is: the National Hurricane Center report says about 65% of electric customers, 75,000 in all, lost power in the City of Tallahassee, plus 20,000 customers in the rest of Leon County.

The Category 1 storm made landfall just east of St. Marks on September 2, 2016, and the NHC called the damage to the city's electrical system the most significant since Hurricane Kate in 1985. Leon County's Hurricane Hermine after-action report records that by Wednesday, September 7, power was restored to approximately 90% of City customers, that nearly all City customers were back by Friday, September 9, and that the remaining outages were generally damage to customers' own service lines from the meter to the pole. A total of 198 mutual aid line crews and staff from nine utilities helped, and the City more than tripled its field workforce.

Residents raised the undergrounding question directly. The same Leon County report lists hazard mitigation related to electrical infrastructure, such as tree maintenance and underground electric, as a principal theme of the community listening sessions, and it recommends that the county and city jointly study hazard mitigation related to electrical infrastructure and tree maintenance. The city's 2025 PSC presentation lists the next busy season, 2024, as the May 10 tornadoes, Hurricane Debby and Hurricane Helene, with zero accidents and mutual aid received.

How does the City of Tallahassee decide which lines go underground?

The City of Tallahassee requires underground lines for all new subdivisions and development and shares the cost of converting existing overhead lines, according to the 2025 PSC presentation.

City of Tallahassee undergrounding rules listed in the May 13, 2025 PSC presentation
SituationCity rule
New subdivisions and developmentUnderground is the city standard
Converting a branch line from overhead to undergroundCity pays 100% if customers pay the delivery point modifications
Converting a feeder circuit from overhead to undergroundCity pays 25% if the requester pays customer delivery and provides easements

Under these rules the city's share is largest for branch conversions, while most of a feeder conversion is the requester's cost. In each case the customer side of the work, changing where the service enters a home or business, is paid by the customer. Neighborhoods in Leon County that want buried lines therefore depend on owners, developers or associations willing to pay their share and grant easements.

Who is responsible for the service line at a Tallahassee house?

Homeowners are responsible for electrical equipment attached to the house, such as the meter box and weather head, while the City of Tallahassee Utilities is responsible for the wire to the pole, the service line and the meter, according to the city's power restoration page.

The distinction matters after a storm. The Tallahassee page says the city is not authorized to repair privately owned equipment; an electrician repairs the weather head, the mast above the meter and the meter box, and after those repairs are completed and inspected the city crew returns to reconnect the service wire and reinstall the meter if it was removed. For underground service lines, the city notes, the responsibilities are a little different, and its diagrams show the split.

What is Tallahassee doing instead of burying everything?

The City of Tallahassee's main alternative to burying lines is hardening and automating the overhead system, through tree trimming, pole inspections, automated TripSavers devices and a federal grid grant for Griffin Heights.

Tallahassee storm hardening measures, from the 2025 PSC presentation and the January 8, 2025 city grant announcement
MeasureDetailSource
Vegetation management8 to 12 feet of clearance, 18 to 24 month cycle; enhanced trimming completed January 2025PSC presentation
Pole inspections8 year inspection cyclePSC presentation
Automated distributionTripSavers devicesPSC presentation
Griffin Heights grant$28.6 million for storm hardening, smart grid equipment and a utility-scale batteryCity of Tallahassee

On January 8, 2025, the City of Tallahassee announced the $28.6 million Grid Resilience and Innovation Partnerships grant from the U.S. Department of Energy, part of a $10.5 billion program the DOE Office of Electricity administers. The money funds hardening poles and other aerial equipment, automated smart distribution equipment that addresses faults and brief outages without dispatching crews, and the city's first utility-scale battery energy storage system, to be installed at the Birmingham Street Substation (BP-2) in Griffin Heights, with estimated annual system fuel cost savings of $160,000. The project engages the RIDER Center at the FAMU-FSU College of Engineering and will issue 30 Clean Energy Trades certificates to trainees. The announcement does not list undergrounding among the funded work.

Why doesn't the state's storm protection law cover Tallahassee?

Florida's storm protection plan law applies to public utilities, and the statute's definition of public utility excludes a municipality, so Tallahassee's city-owned system is not covered by it.

The Legislature's findings in section 366.96, Florida Statutes, state that a majority of power outages during extreme weather in Florida are caused by vegetation blown by the wind, and they promote overhead hardening, the undergrounding of certain distribution lines and vegetation management through plans whose costs utilities recover from customers. Section 366.02 says the term public utility does not include a cooperative organized under the Rural Electric Cooperative Law or a municipality or any agency thereof. Municipal utilities such as Tallahassee instead file storm hardening reports under PSC Rule 25-6.0343, Municipal Electric Utility and Rural Electric Cooperative Reporting Requirements.

That leaves Tallahassee's undergrounding pace to the City Commission and the city budget. As listed on the City of Tallahassee website on October 18, 2026, the commission is Mayor John E. Dailey with Commissioners Jeremy Matlow, Jacqueline "Jack" Porter, Curtis Richardson and Dianne Williams-Cox, and the City Manager is Karen Jumonville.

What must happen before digging near buried lines in Tallahassee?

Florida law requires an excavator to notify the one-call system not less than 2 full business days before digging that is not beneath state waters, under section 556.105, Florida Statutes, and that applies to digging near Tallahassee's buried lines.

The statute also gives the member utility 2 full business days after notification to mark the horizontal route of its underground facility to within 24 inches of either side, using stakes, paint, flags or other suitable means. Digging beneath state waters requires 10 full business days of notice. As more of the Tallahassee and Leon County system is built underground in new subdivisions, those marks are what keep a shovel off a buried line.

Last verified: October 18, 2026. Rechecked for this page: the City's 2025 PSC hurricane workshop slides, its power restoration page and Griffin Heights grant release, the DOE GRIP page, the NHC Hermine report, the Leon County Hermine after-action report, PSC Rule 25-6.0343 and Florida Statutes 366.02, 366.96 and 556.105.

Frequently asked questions

Does Tallahassee require underground power lines in new neighborhoods?

Yes. The City of Tallahassee told the Florida Public Service Commission in May 2025 that its standard is underground service for all new subdivisions and development.

Does the City of Tallahassee help pay to bury existing lines?

Yes. The city pays 100% of a branch line conversion if customers pay the delivery point modifications, and 25% of a feeder circuit conversion if the requester pays customer delivery and provides easements.

How many Tallahassee customers lost power in Hurricane Hermine?

The National Hurricane Center reported that about 65% of City of Tallahassee electric customers, 75,000 in all, lost power, plus 20,000 customers elsewhere in Leon County.

Who regulates undergrounding for Tallahassee?

The City Commission, through the city-owned utility. Florida's storm protection plan statute applies to public utilities, and section 366.02 excludes municipalities from that term; Tallahassee files storm hardening reports under PSC Rule 25-6.0343 instead.

What is the Griffin Heights grid project?

A $28.6 million U.S. Department of Energy GRIP grant announced January 8, 2025, funding pole hardening, smart distribution equipment and the city's first utility-scale battery at the Birmingham Street Substation.

Sources

  1. City of Tallahassee Electric and Gas, Hurricane Preparedness Workshop presentation, Florida PSC, May 13, 2025 https://floridapsc.com/pscfiles/website-files/PDF/Utilities/Electricgas/HurricanePreparationWorkshops/2025%20-%20May%2013%20,2025/05%20Presentation%20by%20City%20of%20Tallahassee.pdf Used for: system size, undergrounding policy, hardening
  2. Tropical Cyclone Report: Hurricane Hermine, National Hurricane Center https://www.nhc.noaa.gov/data/tcr/AL092016_Hermine.pdf Used for: Hermine outages
  3. Leon County Hurricane Hermine After-Action Report, Board workshop December 13, 2016 https://www2.leoncountyfl.gov/coadmin/agenda/Workshops/ws120161213.pdf Used for: restoration timeline, mutual aid, listening sessions
  4. How Power is Restored, City of Tallahassee Utilities https://www.talgov.com/you/power-restoration Used for: responsibility at the house
  5. City Secures $28.6 Million Federal Grant to Strengthen Electric Grid, City of Tallahassee, January 8, 2025 https://www.talgov.com/Main/News/5768 Used for: Griffin Heights grant
  6. Grid Resilience and Innovation Partnerships (GRIP), U.S. Department of Energy https://www.energy.gov/oe/grid-resilience-and-innovation-partnerships-grip-program Used for: $10.5 billion program
  7. Section 366.96, Florida Statutes https://www.flsenate.gov/Laws/Statutes/2024/366.96 Used for: storm protection findings
  8. Section 366.02, Florida Statutes https://www.flsenate.gov/Laws/Statutes/2024/366.02 Used for: public utility definition
  9. Rule 25-6.0343, Florida Administrative Code https://www.flrules.org/gateway/ruleNo.asp?id=25-6.0343 Used for: municipal reporting
  10. Section 556.105, Florida Statutes https://www.flsenate.gov/Laws/Statutes/2024/556.105 Used for: excavation notice
  11. Tallahassee Solar Program, City of Tallahassee Utilities (site footer with City Commission and officials) https://www.talgov.com/you/solar Used for: officeholders
Last updated: October 18, 2026

How this page was made

Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.

This page was fact-checked twice before publishing.

If you see an error, or anything you can show is false, tell us right away and we will take a third look.

Report an error
Quote or describe the part that's wrong.
Explain what's actually true.
Only if you'd like a reply. Never shown publicly.

How we fact-check

Continue exploring

Photo credits