Short answer: Vero Beach voters decide building heights because Section 5.06 of the City Charter bars the City Council from raising the height and density limits in place on August 15, 1989, without a referendum. Section 5.05 adds voter approval for selling or leasing 26 protected city properties. Voters approved the Three Corners lease in 2022 and rejected both downtown density measures on November 5, 2024.
Why do Vero Beach voters, not the City Council, decide building heights?
In Vero Beach the height limit is written into the City Charter, which only city voters can amend. The City of Vero Beach Downtown page quotes Section 5.06, titled Zoning limitations, in full: the building height limitations and density levels existing in the Zoning Ordinance of the City of Vero Beach, Florida, on August 15, 1989, shall not be increased by action of the city council unless such increase shall have first been approved by the electors at a referendum. In plain terms, the 1989 zoning code is a ceiling the Vero Beach City Council cannot raise by ordinance alone.
The city summarizes the rule in one line: Section 5.06 of the City Charter requires any proposed change in height or density limits to be approved by referendum. That covers both how tall buildings can be and how many homes can sit on an acre. Lowering limits, by contrast, is not what Section 5.06 restricts; the charter text speaks only to increases above the August 15, 1989 baseline in Vero Beach.
City leaders describe the rule as a firm barrier. In September 2024, as Indian River County weighed a variance for a 45 foot hotel at the Indian River Mall, Vero Beach 32963 quoted Mayor John Cotugno saying that, unlike the county, Vero Beach is governed by a charter, and that raising height limits downtown or anywhere else within the city limits would need a referendum. The county ordinance at issue limits building heights to 35 feet, and the county can grant variances that the Vero Beach charter does not allow the council to grant on its own.
How tall can buildings be in Vero Beach today?
The limits vary by district. Downtown, the 50-acre core around 14th Avenue carries a 50-foot height limit, according to Vero Beach 32963 reporting from August 2024, which noted that the 2024 density proposal would retain the district's 50-foot height limit. On the beachside, Vero Beach 32963 reported in June 2012 that the existing regulations along Ocean Drive and Cardinal Drive allowed buildings up to a maximum of 50 feet, measured as 35 feet to the eaves and 15 feet to the top of the roof, and that the Indian River Neighborhood Association was then pressing for two-story limits on the west sides of both streets.
The tallest structure on the Vero Beach riverfront predates the rule. When the Three Corners Steering Committee toured the former Big Blue power plant north of the 17th Street bridge in 2020, Planning Director Jason Jeffries reminded city officials that the plant stands 10 feet taller than the city's current height limit, Veronews reported in November 2020. He told them that a 60-foot building could not be built today, which is one reason the fate of Big Blue became a question in the Three Corners planning.
What city land needs a referendum before it can be sold or leased?
A second charter provision, Section 5.05, protects public land. According to the City of Vero Beach Three Corners referendum fact sheet, there are 26 City-owned properties listed in the City Charter, and any sale, lease, trade or gift of these properties has to be approved by Vero Beach citizens by referendum. The list includes Riverside Park, Pocahontas Park, Humiston Beach Park, Jaycee Beach Park, South Beach Park, Alex MacWilliam Park, the Municipal Marina, Leisure Square, Royal Palm Pointe Park, Crestlawn Cemetery, the Old City Nursery, the former city power plant and the city wastewater treatment plant.
The protection shapes everyday decisions at the waterfront. The city's City Marina Zoning Facts page states that land at the City Marina may only be leased for a public or civic purpose which also serves a recreational, artistic, or cultural purpose unless voters approve otherwise. On that basis the City of Vero Beach told residents that a 100-plus room commercial hotel could not be leased space at the marina, and that Bob Summers Park next door, also charter protected and designated Park on the future land use map, could not host a hotel either.
What did the 2022 Three Corners referendum approve?
The former power plant site was on the list of protected land, so redeveloping it required a vote. On November 8, 2022, Vero Beach voters were asked whether to amend Section 5.05 by adding a subsection (c) allowing development of the former power plant site located north of the Alma Lee Loy Bridge pursuant to a long-term lease, for primarily public use and access, including recreation, restaurant, retail and hotel uses consistent with the master concept plan the council adopted by Resolution 2022-03 on February 1, 2022, according to the city fact sheet.
The measure passed easily. Vero Beach 32963 later recalled that 79 percent of city voters approved the proposed development of a dining, retail and recreational hub on the mainland's waterfront. Under the adopted subsection (c), the Three Corners site must keep public access to the waterfront and promenades, and all uses must be open to the public with no private clubs. The fact sheet adds that the vote did not approve any building heights; comprehensive plan, zoning and site plan approvals still go through public Planning and Zoning Board and City Council meetings in Vero Beach.
What happened to the 2024 downtown density referendums?
The City Council adopted a Downtown Master Plan on July 23, 2024, drawn up through a charrette led by Andres Duany of DPZ CoDesign, to bring more housing into Downtown Vero Beach. Because density is capped by Section 5.06, the plan needed voter approval. Vero Beach 32963 reported that Duany had recommended up to 2,500 total units in the downtown core, increasing the district's density to 60 units per acre, but the council settled on a smaller request that it believed had a better chance with voters.
Two charter amendments went on the November 5, 2024 ballot. The city's ballot language asked whether to allow an increase in residential density from the present level of 17 units per acre to a density level of 36 units per acre, with no more than 1,800 units in the Downtown Commercial District, and whether to allow a transfer of development rights program for workforce housing in Mixed Use areas. Council members said the 50-foot downtown height limit would stay the same under either measure.
Both failed. WFLX reported on November 6, 2024, that about 65 percent of Vero Beach voters opposed the density increase, with over 5,000 votes against and around 2,800 in favor. Veronews columnist Ray McNulty wrote that more than 65 percent of voters opposed the referendum to increase residential density from 17 to 36 units per acre, and that more than 63 percent voted against the transfer of development rights. Concern that a density increase could lead to taller buildings, the slippery slope described in Vero Beach 32963 that September, ran through the campaign even though neither question touched the height limit.
Who decides the next step after the 2024 vote?
After the defeat the Vero Beach City Council turned to changes that need no referendum. Veronews reported in February 2025 that the council convened a two-hour special-call meeting on January 28, 2025, and that the city was relying on its downtown Economic Development Zone and planned improvements such as upgraded lighting, better signage and a renovation of Pocahontas Park. Any future attempt to raise density or height in Vero Beach would again need a citywide vote under Section 5.06.
The council that would place such a question on the ballot, according to the City of Vero Beach City Council page, is Mayor John E. Cotugno, Vice Mayor Taylor Dingle and Councilmembers Linda Moore, John Carroll and Aaron Vos. Last verified: October 8, 2026, on the City of Vero Beach website, using its Downtown referendum and City Council pages.
Frequently asked questions
Can the Vero Beach City Council raise the height limit by ordinance?
No. Section 5.06 of the Vero Beach City Charter says height limits and density levels in the zoning ordinance on August 15, 1989, cannot be increased by the council unless city electors first approve the increase at a referendum.
What is the height limit in downtown Vero Beach?
Vero Beach 32963 reported in August 2024 that the 50-acre downtown core around 14th Avenue has a 50-foot height limit, and that the 2024 density proposal would have kept it unchanged even if voters had approved it.
Did Vero Beach voters approve the 2024 downtown referendums?
No. On November 5, 2024, more than 65 percent voted against raising downtown density from 17 to 36 units per acre, and more than 63 percent voted against a transfer of development rights program, according to Veronews.
Why did Three Corners need a referendum?
The former power plant site north of the Alma Lee Loy Bridge is one of 26 properties protected by Section 5.05 of the charter. A November 2022 referendum, approved by 79 percent of city voters, allowed long-term leases there for mostly public uses.
Does the Vero Beach rule apply in unincorporated Indian River County?
No. The charter covers only the City of Vero Beach. Indian River County sets its own 35-foot limit by ordinance and can consider variances, as it did for a proposed hotel at the Indian River Mall in 2024.
Sources
- Downtown (Downtown Referendum and Section 5.06), City of Vero Beach https://www.covb.org/555/Downtown Used for: Charter Section 5.06 text, August 15, 1989 baseline, November 5, 2024 ballot questions, July 23, 2024 master plan adoption
- Three Corner's Referendum Fact Sheet, City of Vero Beach https://www.covb.org/597/Three-Corners-Referendum-Fact-Sheet Used for: Charter Section 5.05, 26 protected properties, Three Corners ballot question and subsection (c)
- City Marina Zoning Facts, City of Vero Beach https://www.covb.org/598/City-Marina-Zoning-Facts Used for: Marina lease limits under Section 5.05, hotel question
- Referendums put breadth of downtown development in voters' hands (Vero Beach 32963, August 1, 2024) https://vb32963online.com/STORIES 2024/AUGUST 2024/VB32963_Referendums_Put_Breadth_Of_Downtown_Development_In_Voters_Hands_Issue31_080124.html Used for: Density proposal, 50-foot downtown height limit, Duany recommendation, council vote
- Height-limit issue gives rise to fears of 'slippery slope' (Vero Beach 32963, September 26, 2024) https://vb32963online.com/STORIES 2024/SEPTEMBER 2024/VB32963_Height-Limit_Issue_Gives_Rise_To_Fears_Of_Slippery_Slope_Issue39_092624.html Used for: Charter safeguard statements, county 35-foot limit and mall variance, 79 percent Three Corners vote
- Voters say no to residential changes in downtown Vero Beach (WFLX, November 6, 2024) https://www.wflx.com/2024/11/06/voters-say-no-residential-changes-downtown-vero-beach Used for: November 2024 referendum result
- Much can still be done to enhance downtown Vero (Veronews, November 15, 2024) https://veronews.info/2024/11/15/much-can-still-be-done-to-enhance-downtown-vero/ Used for: Referendum percentages for both questions
- Council ignoring voters' will on Downtown Vero (Veronews, February 14, 2025) https://veronews.info/2025/02/14/council-ignoring-voters-will-on-downtown-vero/ Used for: January 28, 2025 special-call meeting, Economic Development Zone, planned downtown improvements
- IRNA concerned oceanside height limits at risk (Vero Beach 32963, June 7, 2012) https://vb32963online.com/STORIES 2012/JUNE 2012/VB32963_IRNA_Oceanside_Height_Limit_Issue23_060712.html Used for: Ocean Drive and Cardinal Drive height rules in 2012
- North of bridge, dismantle Big Blue or turn it into riverfront centerpiece? (Veronews, November 5, 2020) https://veronews.info/?p=141746 Used for: Big Blue height compared with city height limit
- City Council, City of Vero Beach https://www.covb.org/283/City-Council Used for: Current council members, verified October 8, 2026