St. Johns Heritage Parkway widening — Palm Bay, Florida

Palm Bay is designing four lanes for three miles of St. Johns Heritage Parkway between Malabar Road and Emerson Drive, and construction money has not been found.


Short answer: No construction date has been set for widening St. Johns Heritage Parkway in Palm Bay. The City of Palm Bay is designing four lanes on about three miles of the parkway, from Malabar Road to north of Emerson Drive, with design expected to finish in July 2026 at an estimated $3,200,000, and the city lists construction as currently unfunded.

Last verified: October 12, 2026, against the sources listed at the end of this page.

When will St. Johns Heritage Parkway be widened to four lanes?

No construction date exists yet: Palm Bay expects to finish designing the four lanes of St. Johns Heritage Parkway in July 2026, and the city lists construction as currently unfunded (City of Palm Bay).

The design phase started in December 2024 under the City of Palm Bay Public Works Department, with an estimated design completion date of July 2026 and an estimated design cost of $3,200,000 (SJHP widening project page). The same page says the next phase, construction, is currently unfunded, so no contractor, bid date or lane closure schedule exists for the widening between Malabar Road and Emerson Drive. Last verified: October 12, 2026, on the City of Palm Bay Public Works project page for the parkway.

Palm Bay is designing ahead of the money on purpose. The Public Works projects page says the city already owns the necessary property and associated drainage for the future project, which positions the city to seek construction funding (Palm Bay Public Works projects).

The widening reached the Space Coast Transportation Planning Organization's long range plan as a need, not as a funded project. The Advance 2050 needs list carries St. Johns Heritage Pkwy from Malabar Rd to US 192 as a widening to four lanes over 6.09 miles with a total cost of $147,927,610 (Space Coast TPO Advance 2050 LRTP, Appendix F). That row covers a longer stretch than the Palm Bay design, which stops north of Emerson Drive.

Which part of the parkway would get four lanes?

The Palm Bay design covers about three miles of St. Johns Heritage Parkway, from Malabar Road north to a point north of Emerson Drive, which today is a two-lane undivided road (City of Palm Bay).

Three intersections shape the design. The Public Works projects page says the designers are evaluating traffic signals at Emerson Drive, Pace Drive and the planned bridge connection at Fred Poppe Regional Park, and that a roundabout or a traffic signal is being considered for the Malabar Road and St. Johns Heritage Parkway intersection (Palm Bay Public Works projects).

The Fred Poppe Regional Park connection is its own project. On December 21, 2023 the Palm Bay City Council approved a Kimley-Horn task order of $435,095 for engineering and design of the bridge and roadway entrance to Fred Poppe Regional Park from St. Johns Heritage Parkway, paid with $217,548 each from the 32907 and 32908 recreation impact fee nexus areas (council minutes, December 21, 2023). The city engineer told the Infrastructure Advisory and Oversight Board in November 2023 that the new entrance would give the park a second way in, since there was only one way in and out of the park (IAOB minutes, November 27, 2023).

New neighborhoods line the corridor. The same December 2023 council meeting took up the final plat for Riverwood at Everlands Phase 1, a 124-lot subdivision east of and adjacent to St. Johns Heritage Parkway in the vicinity north of Emerson Drive (council minutes, page 8). Signal plans for the Emerson Drive intersection are being designed under a separate contract with Consor North America, Inc., and the city and developers are working so that the signal is installed in consideration of the future widening (Palm Bay Public Works projects); Emerson Drive has its own page in this Palm Bay transportation section.

Who is paying for the parkway widening design?

The Palm Bay design is partially funded by a $1.5 million state appropriation plus $1,737,000 in city transportation impact fees (Public Works projects; council minutes).

St. Johns Heritage Parkway widening money as stated in Palm Bay records
ItemAmountSource and date
State funding reported for widening SJHP to four lanes$1.5 millionIAOB minutes, November 27, 2023
Transportation Impact Fee funds with Resolution 2023-48$1,737,000Council minutes, December 21, 2023
Estimated design project cost$3,200,000SJHP project page
Total design and engineering cost$3.3 millionPublic Works projects page
ConstructionCurrently unfundedSJHP project page
Long range need, Malabar Rd to US 192$147,927,610Space Coast TPO Advance 2050

The two city figures come from two city pages and are shown as each page states them: the St. Johns Heritage Parkway project page lists an estimated design project cost of $3,200,000, while the Public Works projects page gives a total design and engineering cost of $3.3 million (Palm Bay Public Works projects). Adding the two cited funding sources gives $1,500,000 plus $1,737,000, or $3,237,000, which sits between them.

The impact fee share was set on December 21, 2023, when the Palm Bay City Council adopted Resolution 2023-48, authorizing a State-Funded Grant Agreement with the Florida Department of Transportation for the St. Johns Heritage Parkway widening (council minutes, page 17). A month earlier the city engineer had told the Infrastructure Advisory and Oversight Board that the city would have to add another $1.8 million to the state money (IAOB minutes). The design is run through FDOT's Local Agency Program as a Class B project and is listed in the Space Coast TPO Fiscal Year 2025-2029 Transportation Improvement Program (SJHP widening project page).

Why does Palm Bay want four lanes on St. Johns Heritage Parkway?

Palm Bay gives four reasons for widening St. Johns Heritage Parkway: less congestion, more room for emergency evacuation, a better level of service on Malabar Road and the parkway, and shorter emergency response times (City of Palm Bay).

Traffic control has already changed at Malabar Road. At the September 23, 2024 meeting of the Palm Bay Infrastructure Advisory and Oversight Board, staff reported that portable signals were up and working at St. Johns Heritage Parkway and Malabar Road and appeared to be helping with the traffic problems there (IAOB minutes, September 23, 2024). At the same meeting the board asked about the widening, and staff said the city was negotiating contracts to design it.

Growth around Emerson Drive drove the earlier work. In November 2023 the city engineer described numerous residential developments in the area, a board member noted Everlands West, and the engineer said the Emerson Drive intersection warranted a traffic signal based on traffic studies (IAOB minutes, November 27, 2023). The Public Works projects page says the city and developers are working together so that signal work at Emerson Drive and the parkway is installed in consideration of the future widening (Palm Bay Public Works projects).

What has happened on the widening so far?

Palm Bay has moved the parkway widening from a state grant in 2023 to a design under way since December 2024 (SJHP widening project page) and a public meeting held October 6, 2025 (Palm Bay Public Works projects).

St. Johns Heritage Parkway widening timeline in Palm Bay
DateStep
November 27, 2023City engineer reports $1.5 million in state funding for four lanes (IAOB)
December 21, 2023Council adopts Resolution 2023-48 with $1,737,000 in impact fees (council)
September 23, 2024City negotiating design contracts (IAOB)
December 2024Design starts with Scalar Consulting Group Inc. (project page)
October 6, 2025Public meeting with nearby residents (projects page)
July 2026Estimated design completion (project page)

The Palm Bay project page posts the design record: a kickoff newsletter from May 2025, a newsletter from September 2025, a public meeting summary, a concept plan roll plot, display boards, a Cultural Resources Assessment Survey, a Natural Resources Evaluation Addendum, a Noise Study Report and a Traffic Analysis Report (SJHP widening project page).

Federal rules apply because the work uses the Local Agency Program. The St. Johns Heritage Parkway page states that the environmental review for the project is carried out by the Florida Department of Transportation under 23 U.S.C 327 and a Memorandum of Understanding dated May 26, 2022 with the Federal Highway Administration (City of Palm Bay).

How can Palm Bay residents follow the parkway widening?

Palm Bay Public Works runs the parkway widening from City Hall at 120 Malabar Road, and its project page offers a mailing list, a comment form and a project manager line at (321) 726-5665 x 6215 (City of Palm Bay).

Updates also surface at the Palm Bay Infrastructure Advisory and Oversight Board, the citizen board that hears Public Works reports on the parkway, its signals at Malabar Road and Emerson Drive and the Fred Poppe Regional Park entrance (IAOB minutes, September 23, 2024). The design itself is listed in the Space Coast TPO Fiscal Year 2025-2029 Transportation Improvement Program (SJHP widening project page).

The broader St. Johns Heritage Parkway and its I-95 interchange are covered on their own page in this section, as are Malabar Road and Emerson Drive. This page tracks only the four-lane design between Malabar Road and north of Emerson Drive, which the City of Palm Bay lists at approximately three miles (SJHP widening project page).

Frequently asked questions

Is St. Johns Heritage Parkway in Palm Bay being widened now?

Not yet. The City of Palm Bay is only designing the widening between Malabar Road and north of Emerson Drive. The city project page gives July 2026 as the estimated design completion date and says construction is currently unfunded, so no construction start has been announced.

How long is the planned widening of the parkway?

Approximately three miles, from Malabar Road north to a point north of Emerson Drive, according to the City of Palm Bay project page. That segment is a two-lane undivided road today and the design would make it four lanes.

Who is designing the St. Johns Heritage Parkway widening?

The City of Palm Bay Public Works Department manages the design, with Scalar Consulting Group Inc. as consultant. It is a Florida Department of Transportation Local Agency Program Class B project and is listed in the Space Coast TPO Fiscal Year 2025-2029 Transportation Improvement Program.

What will happen at the Malabar Road end of the parkway?

The Palm Bay Public Works projects page says a roundabout or a traffic signal is being considered for the Malabar Road and St. Johns Heritage Parkway intersection. Portable signals were already working there by September 2024, according to Infrastructure Advisory and Oversight Board minutes.

Does Palm Bay already own the land for the wider parkway?

Yes. The Public Works projects page states that the City of Palm Bay already owns the necessary property and associated drainage for the future project, which positions the city to seek construction funding once design is complete.

Sources

  1. St. Johns Heritage Parkway (SJHP) Four-Lane Widening from Malabar Road to North of Emerson Drive, City of Palm Bay Public Works https://www.palmbayfl.gov/government/city-departments-f-to-z/public-works/projects/st-johns-heritage-parkway-sjhp-four-lane-widening-from-malabar-road-to-north-of-emerson-drive Used for: limits, length, schedule, design cost, unfunded construction, consultant, LAP Class B, TIP listing, purpose, study documents, environmental review
  2. Public Works Projects, City of Palm Bay (Road Capacity Improvement Update) https://www.palmbayfl.gov/government/city-departments-f-to-z/public-works/projects Used for: state appropriation, signal evaluation at Emerson, Pace and Fred Poppe bridge, Malabar Road roundabout or signal, $3.3 million design, right of way owned, October 6, 2025 meeting, Emerson signal coordination
  3. Palm Bay City Council Regular Meeting 2023-33 minutes, December 21, 2023, page 16 https://www.palmbayfl.gov/home/showpublisheddocument/26828/638412778907230000#page=16 Used for: Kimley-Horn task order for the Fred Poppe Regional Park bridge entrance, Resolution 2023-48 item and $1,737,000 TIF
  4. Palm Bay City Council Regular Meeting 2023-33 minutes, December 21, 2023, page 17 https://www.palmbayfl.gov/home/showpublisheddocument/26828/638412778907230000#page=17 Used for: adoption of Resolution 2023-48
  5. Palm Bay City Council Regular Meeting 2023-33 minutes, December 21, 2023, page 8 https://www.palmbayfl.gov/home/showpublisheddocument/26828/638412778907230000#page=8 Used for: Riverwood at Everlands Phase 1 plat beside the parkway north of Emerson Drive
  6. Palm Bay Infrastructure Advisory and Oversight Board minutes, November 27, 2023, page 2 https://www.palmbayfl.gov/home/showpublisheddocument/26758/638388521755900000#page=2 Used for: Emerson signal warranted, $1.5 million state funding plus $1.8 million city share, Fred Poppe bridge entrance
  7. Palm Bay Infrastructure Advisory and Oversight Board minutes, September 23, 2024, page 2 https://www.palmbayfl.gov/home/showpublisheddocument/27681/638730498306930000#page=2 Used for: design contract negotiation, portable signals at Malabar Road
  8. Space Coast TPO Advance 2050 Long Range Transportation Plan, Appendix F needs list, page 3 https://www.spacecoasttpo.com/home/showpublisheddocument/3052/639008738332770000#page=3 Used for: St. Johns Heritage Pkwy Malabar Rd to US 192 widening need, 6.09 miles, $147,927,610
Last updated: October 12, 2026