St. Lucie West Boulevard Projects, Port St. Lucie

Each intersection and widening project on the St. Lucie West corridor, what it adds, what it costs and how the city records its status.


Short answer: Port St. Lucie lists intersection projects where St. Lucie West Boulevard meets California, Peacock, Cashmere and Bayshore boulevards, plus a widening of SW California Boulevard to four lanes. Cashmere and Bayshore are complete on both city pages, Peacock is complete on the half-cent page but listed as upcoming on the project page, and FDOT reported its new I-95 bridge and ramps complete in December 2024.

Last verified: October 22, 2026, against the sources listed at the end of this page.

What road projects has Port St. Lucie listed for St. Lucie West Boulevard?

Port St. Lucie lists intersection and widening projects on or next to St. Lucie West Boulevard, plus the state's I-95 bridge and ramp project, on two city pages that each record a status.

St. Lucie West Boulevard area projects on two City of Port St. Lucie pages
ProjectSt. Lucie West Blvd. Projects pageHalf-Cent Sales Tax Projects page
California Blvd. intersectionUpcoming$2 million, in progress
SW California Blvd. wideningUpcoming$15.1 million, in progress
Peacock Blvd. intersectionUpcoming, completion anticipated February 2026$204,754, completed
SW Cashmere Blvd. intersectionCompleted$829,883, completed
NW Bayshore Blvd. intersectionCompleted$462,096, completed
I-95 bridge and ramps (FDOT)CompletedNot listed

The middle column comes from the Public Works St. Lucie West Blvd. Projects page, which sorts the work into upcoming and completed lists and points readers to the Capital Improvement Projects tracker map for phases and schedules. The right column comes from the status legend and cost lines on the Half-Cent Sales Tax Projects page, where the St. Lucie West group as a whole carries $18.3 million.

Why is St. Lucie West Boulevard being rebuilt intersection by intersection?

The city calls St. Lucie West Boulevard one of the busiest corridors in Port St. Lucie and says its intersections need added turn lanes to improve traffic and pedestrian safety.

The Half-Cent Sales Tax Projects page describes the boulevard as connecting several commercial districts, shopping centers, institutional uses and residential developments from Bayshore Boulevard to Interstate 95, and states that the corridor is in need of major intersection improvements. The same page says California Boulevard, south of St. Lucie West Boulevard, needs widening from two to four lanes because the corridor is failing at peak hour travel times. Its stated solution is the set of intersection projects plus the California widening, which the city expects to raise traffic capacity and pedestrian mobility.

Planning money has been set aside for the boulevard itself as well. The city's FY 2023-24 Adopted Budget Book included a Project Development and Environmental (PD&E) study and design for widening St. Lucie West Boulevard and Southbend Boulevard, and listed Saint Lucie West Blvd Widening Improvements at $3.5 million within its five-year capital program.

What changes at California Boulevard and St. Lucie West Boulevard?

At California Boulevard, the Port St. Lucie project adds a second left-turn lane on all four approaches and upgrades the signal mast arms, and a separate project widens SW California Boulevard to four lanes south to Crosstown Parkway.

The St. Lucie West Blvd. Projects page spells out the intersection work: a second westbound and a second eastbound left-turn lane on St. Lucie West Boulevard at California Boulevard, and a second northbound and a second southbound left-turn lane on California Boulevard. The half-cent page describes the need the same way, saying all four legs of the intersection need an additional dual left-turn lane, and lists the intersection at $2 million (Half-Cent Sales Tax Projects).

The widening covers SW California Boulevard from Crosstown Parkway to St. Lucie West Blvd., going from two lanes to four with drainage improvements, sidewalks and landscaping (project list). The half-cent page carries California Widening at $15.1 million, and the FY 2023-24 budget lists the same $15.1 million figure for California Widening in its five-year capital program.

What was built at Peacock Boulevard and St. Lucie West Boulevard?

The Peacock Boulevard project in Port St. Lucie adds turn and through lanes at the intersection nearest the I-95 interchange, designed to complement the state's new St. Lucie West Boulevard bridge over I-95.

The St. Lucie West Blvd. Projects page lists an additional southbound turn lane, a westbound through lane, an eastbound left-turn lane, a westbound right-turn lane and a northbound through lane to Courtyard Circle. A city notice published April 24, 2025 described the same work for residents: a third westbound travel lane connecting directly to the I-95 North on-ramp, and NW Peacock Boulevard expanded from NW Courtyard Circle to St. Lucie West Boulevard with a third northbound lane and a third southbound lane, along with upgraded sidewalks, drainage and landscaping.

Three city records give timing for this St. Lucie West project. The April 2025 notice said construction was scheduled to commence in May 2025 with completion anticipated by Spring 2026, while the project page states completion was anticipated in February 2026, and the half-cent page marks the Peacock intersection completed at $204,754. The FY 2023-24 budget had listed beginning the design of the St Lucie West Blvd / Peacock Blvd intersection improvements among that year's Public Works objectives (budget book). The residents' coffee meeting on the project was held Monday, May 5, 2025, from 8 to 10 a.m. at South County Regional Stadium, 560 NW University Blvd. (city notice).

Which St. Lucie West Boulevard projects are finished?

Both city pages list the Cashmere Boulevard and Bayshore Boulevard intersections in St. Lucie West as completed, and the Florida Department of Transportation reported its St. Lucie West Boulevard bridge and ramp project complete in December 2024.

At Cashmere Boulevard, eastbound St. Lucie West Boulevard gained its own right-turn lane and northbound Cashmere gained a second lane for left turns. At Bayshore Boulevard, it extended the southbound right-turn lane at Prima Vista/St. Lucie West Boulevard and added a southbound through lane. Both descriptions are on the city's St. Lucie West Blvd. Projects page, and the half-cent page lists Cashmere at $829,883 and Bayshore at $462,096.

The same two cross streets were rebuilt farther north as well. The Half-Cent Sales Tax Projects page marks roundabouts at Torino Parkway and California Boulevard ($1,081,866) and at Torino Parkway and Cashmere Boulevard ($1,096,404) as completed, explaining that those three-legged Port St. Lucie intersections were failing at peak morning and evening hours as drivers backed up waiting to turn left. The same page lists those roundabouts under Torino Intersection Improvements at $2 million.

The I-95 work was a state project. The city page says FDOT managed the work, which added a new eastbound bridge carrying the boulevard across I-95, turned the older span into a crossing for two lanes of westbound traffic and added new I-95 entrance and exit ramps. FDOT's year-end news release of December 20, 2024 listed the completion of the St. Lucie West Boulevard Widening Project in St. Lucie County, with a new bridge over I-95, the widening and rebuilt I-95 ramps. Questions about city intersection work go to 1PSL at 772-871-1775. Last verified: October 22, 2026, with each figure traced back to the St. Lucie West project list, the half-cent status legend and costs, the April 2025 Peacock notice, the FY 2023-24 budget objectives and FDOT's 2024 year-end release.

Frequently asked questions

Is the Peacock Boulevard intersection work in St. Lucie West finished?

The city records differ. The half-cent sales tax page marks the Peacock intersection completed, while the St. Lucie West Blvd. Projects page lists it under upcoming with completion anticipated in February 2026, and an April 2025 notice gave Spring 2026.

Will California Boulevard in Port St. Lucie be widened?

The city lists a project to widen SW California Boulevard from two to four lanes between Crosstown Parkway and St. Lucie West Blvd., with drainage, sidewalks and landscaping, carried at $15.1 million on the half-cent sales tax page.

Who built the new St. Lucie West Boulevard bridge over I-95?

The Florida Department of Transportation. Its project added an eastbound bridge, turned the older span into a westbound crossing and rebuilt the interstate ramps, and FDOT reported the project complete in its December 2024 year-end release.

How are the St. Lucie West Boulevard intersection projects paid for?

The voter-approved half-cent sales tax project list carries a St. Lucie West group at $18.3 million, including Cashmere at $829,883, California at $2 million, Peacock at $204,754 and Bayshore at $462,096.

Sources

  1. St. Lucie West Blvd. Projects, City of Port St. Lucie https://www.cityofpsl.com/Government/Your-City-Government/Departments/Public-Works/Public-Works-Projects-Programs/St-Lucie-West-Blvd-Projects Used for: project scopes and status
  2. Half-Cent Sales Tax Projects, City of Port St. Lucie https://www.cityofpsl.com/Government/Your-City-Government/Departments/Public-Works/Public-Works-Projects-Programs/Half-Cent-Sales-Tax-Projects Used for: costs, status marks, corridor need
  3. City of Port St. Lucie FY 2023-24 Adopted Budget Book https://www.cityofpsl.com/files/assets/public/v/1/departments/office-of-management-amp-budget/documents/fy-23-24-adopted-budget.pdf Used for: PD&E, Peacock design, CIP lines
  4. FDOT news release, December 20, 2024 https://www.fdot.gov/info/co/news/2024/12202024 Used for: I-95 bridge project completion
  5. St. Lucie West Blvd and NW Peacock Blvd Intersection Improvements (April 24, 2025) https://www.cityofpsl.com/News/2025/St.-Lucie-West-Blvd-and-NW-Peacock-Blvd-Intersection-Improvements Used for: Peacock scope, meeting, timing
Last updated: October 22, 2026

Published by Rytas Dirse, Solo Founder & AI Architect

Built with AI, held to quality gates. US sources, US brands, facts only.

How this page was made

Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.

If you see an error, or anything you can show is false, tell us right away and we will take a third look.