Harbour Island — Tampa, Florida

A dredged port island at the mouth of the Hillsborough River, named for a Seaboard railroad engineer and remade as Harbour Island after 1981.


Short answer: Harbour Island was Seddon Island, a port island built from dredged sand after 1906 at the mouth of the Hillsborough River in Tampa and named for railroad engineer W. L. Seddon. After decades of rail yards and phosphate elevators, Beneficial Corporation announced a mixed-use plan in 1981, renamed the island, and opened it in 1985 with an elevated People Mover that ran until January 1999.

How did Seddon Island become Harbour Island?

Harbour Island began as Seddon Island, a pile of dredged sand that took shape after 1906 at the mouth of the Hillsborough River in downtown Tampa. For roughly seven decades the island served the railroad and the port. The name change arrived with a 1981 redevelopment plan from Beneficial Corporation, which proposed offices, hotels, shops and homes on the old freight yard, according to a history published by Tampa Magazine on May 19, 2020.

The rename marked a shift in purpose rather than a new piece of land. The same acreage that once held lumber yards and phosphate elevators became a planned district reached by bridge from Franklin Street and Channelside Drive. The island's story therefore runs through three eras: an engineered port island built by the Seaboard Air Line Railroad, a cleared industrial tract waiting through the 1960s and 1970s, and the mixed-use Harbour Island that opened in stages from 1985 onward, beginning with a hotel, the Shops on Harbour Island and an elevated People Mover from downtown Tampa.

How was Seddon Island built out of the Grassy Islands?

Before 1906, Tampa Magazine reports, the site was mostly water plus part of an island commonly known as Little Grassy Island. Little Grassy and its bigger neighbor, Big Grassy Island, were delta islands at the river mouth that sat empty except for mangroves, crabs and rabbits. The change came when the United States Army Corps of Engineers dredged a shipping channel through Hillsborough Bay to reach downtown Tampa, and that channel sliced through Little Grassy Island.

The dredging left a large surplus of sand. Engineers piled it along the eastern side of the new channel, near and on top of Little Grassy Island, building a larger island for port use. W. L. Seddon, an engineer for the Seaboard Air Line Railroad, which was the main benefactor of the dredging, is credited with directing the work, and the island carried his name for most of the twentieth century.

Garrison Channel was cut in the same campaign and became part of the new Port of Tampa, leaving Seddon Island separated from the downtown Tampa shoreline by open water. Seaboard freight trains crossed to the island on a steel bridge supplied by the Scherzer Rolling Lift Bridge Company of Chicago and set in place in 1908, the link that turned a spoil island into a working rail terminal.

What stood on Seddon Island during its industrial decades?

Rail service brought cargo almost immediately. Tampa Magazine records that the port's first phosphate shipment came the year after the 1908 bridge, and that docks, wharves, warehouses and phosphate elevators lined the downtown Tampa waterfront from then until the 1960s. Lumber yards shared Seddon Island with the elevators, and the whole riverfront down to the estuary that is now the Water Street district was industrializing around it.

Cleanup came slowly. Starting in the 1950s, under Mayor Curtis Hixon, the City of Tampa began clearing its industrial waterfront, a job expected to take a decade that stretched across almost half a century. The riverfront between Kennedy Boulevard and Cass Street was handled first, where a public library, a parking garage and a convention center named for Hixon replaced warehouses and rail tracks. The southern end of downtown, including Seddon Island, waited until the late 1970s, by which time the island was described as burnt out docks with feral pigs.

The public infrastructure of that era outlasted the elevators. The American Society of Civil Engineers reports that the 54-inch Harbour Island Force Main, a sewer pipeline that crosses the island toward the treatment plant near Port Tampa Bay, was placed in operation in 1951, long before anyone lived on the island.

What did the 1981 Harbour Island plan propose?

Among the first private projects announced for the southern end of downtown Tampa, in 1981, was Harbour Island. Tampa Magazine describes the Beneficial Corporation plan as a mixed-use development of office space, hotels, shops and homes, most of them multi-family units ranging from two-story townhomes to tall apartment buildings. Many observers at the time considered a project of that scale so close to downtown a folly.

The retail piece struggled. The Shops on Harbour Island, a mall-like center meant to draw diners and shoppers day and night, opened before many residents lived on the island and faded once the novelty wore off, since few people from elsewhere in Tampa crossed Garrison Channel to support it. The housing plan, by contrast, broadened over time from mostly multi-family buildings into a mix of single-family homes, townhomes and high-rise towers, and the island came to house thousands of residents.

Tampa Magazine also credits Harbour Island with setting a pattern for the southern edge of downtown Tampa. The later public and private investments it lists along the channel include the Tampa Convention Center, the Florida Aquarium, Amalie Arena, the Tampa Bay History Center, three hotels and the Water Street Tampa development.

What was the Harbour Island People Mover?

The People Mover was the transit link Beneficial built to tie the island to downtown Tampa. A 2018 conference paper archived by Michigan Technological University records that service began in June 1985, with President Ford taking part in the opening of the development and riding the inaugural trip. Otis Transportation Systems manufactured the system, which ran on a 2,500-foot elevated concrete guideway between a shopping center on Harbour Island and a parking garage beside downtown.

The original concept was even more unusual. Tampa Magazine notes that planners first proposed cable cars hung overhead, carrying passengers from the center of downtown over Franklin Street and Garrison Channel; the design changed to a single-track shuttle running high above the street from the Fort Brooke Parking Garage to the hotel building. Modern Cities identifies the downtown end as the Old Fort Brooke parking garage and gives the opening date as June 25, 1985.

Ridership never matched the ambition. The Michigan Tech paper states that ridership remained low while operating costs grew, and that Beneficial tried to sell the privately owned line to the Hillsborough Area Regional Transportation Authority (HART). Operations ceased in January 1999 and the guideway was torn down within the year. Money from the closure settlement went into an endowment for operating the TECO vintage streetcar line that serves downtown Tampa and Ybor City today.

Which City of Tampa projects have reshaped Harbour Island since 2018?

Two City of Tampa projects reached Harbour Island after 2018. The Harbour Island Complete Streets project covered Knights Run Avenue, from South Harbour Island Boulevard to Beneficial Drive, and Beneficial Drive from Knights Run Avenue to Channelside Drive, four-lane collector roads carrying roughly 15,380 to 16,560 vehicles a day. The plan rehabilitated both roads, added two raised pedestrian crosswalks and bicycle lanes, narrowed lanes to ten feet, put a two-foot buffer on the bike lane across the Beneficial Bridge, and lowered the Beneficial Drive speed limit from 40 MPH to 25 MPH. The city held its public information meeting at the Tampa Bay History Center on October 2, 2018.

The second project concerned the 1951 sewer line. In 2017, during maintenance on the Harbour Island Bridge, contractors found leaks in the force main hung beneath the bridge deck, according to ASCE. When the city floated replacement routes, Bay News 9 reported on May 16, 2018 that island residents objected to a plan that would dig up sidewalks, roads and yards along the island's spine. The FOX 13 coverage of August 16, 2023 quotes the city's wastewater director saying the densely built island left no room for a new pipe, so the route went around it.

The answer was a tunnel under the water rather than a trench across Harbour Island. The City of Tampa reported on August 14, 2023 that the replacement began in August 2022 and that a 3,200-foot micro-tunnel had been bored 60 feet below the bay surface, with its receiving shaft in Cotanchobee Fort Brooke Park on Garrison Channel. On June 3, 2024 the city announced that all flow from the force main on Harbour Island had been diverted to a new 78-inch pipeline running about 13,700 feet to the Howard F. Curren Advanced Wastewater Treatment Plant, an $83 million job funded through the PIPES program; earlier 2023 reports put the cost at $79 million.

Frequently asked questions

Who was Seddon Island named for?

Seddon Island took its name from W. L. Seddon, an engineer with the Seaboard Air Line Railroad who directed the dredge-and-fill work that built the island after 1906, according to Tampa Magazine. The name stayed in use until the 1981 Harbour Island plan.

When did the Harbour Island People Mover run?

The People Mover carried riders between downtown Tampa and Harbour Island from June 1985 until January 1999. Low ridership and rising costs ended service, and the elevated guideway over Garrison Channel was demolished within the year, per a 2018 Michigan Tech paper.

What happened to the money from closing the People Mover?

Settlement money from the People Mover closure was placed in an endowment that helps cover operating costs for the TECO vintage streetcar line in downtown Tampa and Ybor City, according to the 2018 history archived by Michigan Technological University.

Which roads serve Harbour Island?

City of Tampa records name South Harbour Island Boulevard, Knights Run Avenue and Beneficial Drive, which crosses the Beneficial Bridge toward Channelside Drive. The Harbour Island Bridge links the island north to Franklin Street downtown.

Why did Tampa tunnel under the bay instead of rebuilding the sewer line on Harbour Island?

City officials told FOX 13 in August 2023 that the island was too densely built for a new large pipe. The replacement for the 1951 Harbour Island Force Main was routed through a micro-tunnel under the Ybor Turning Basin to Cotanchobee Park instead.

Sources

  1. Harbour Island: A Tampa Neighborhood's History (Tampa Magazine, May 19, 2020) https://tampamagazines.com/harbour-island-a-tampa-neighborhoods-history/ Used for: Seddon Island creation 1906, Little Grassy Island, W. L. Seddon, Garrison Channel, 1908 Scherzer bridge, phosphate era, Hixon waterfront cleanup, 1981 Beneficial plan, People Mover cable car origin, Shops on Harbour Island, later downtown investment
  2. History of the Tampa Harbour Island People Mover (Sproule and Smith, Michigan Tech Digital Commons, 2018) https://digitalcommons.mtu.edu/michigantech-p/15194 Used for: People Mover opening June 1985, President Ford, Otis, 2,500-foot guideway, HART sale efforts, January 1999 closure, demolition, TECO streetcar endowment
  3. Discovering the downtown Tampa you didn't know (Modern Cities, August 2016) https://www.moderncities.com/article/2016-aug-discovering-the-downtown-tampa-you-didnt-know-page-3 Used for: People Mover downtown terminus at Old Fort Brooke parking garage, June 25, 1985 opening, replacement by TECO Line Streetcar
  4. Harbour Island Complete Streets (City of Tampa) https://www.tampa.gov/tss-transportation/info/projects/completed/hicompletestreets Used for: Knights Run Avenue and Beneficial Drive improvements, traffic volumes, Beneficial Bridge bike lane, speed limit change, October 2, 2018 public meeting
  5. Revolutionary Wastewater Project Reaches Key Milestone in Tampa Bay (City of Tampa, August 14, 2023) https://www.tampa.gov/news/2023-08/revolutionary-wastewater-project-reaches-key-milestone-tampa-bay-125841 Used for: force main installed 1951 on Harbour Island, project start August 2022, micro-tunnel 3,200 feet and 60 feet deep, Cotanchobee Park
  6. Major Wastewater Project Completed (City of Tampa, June 3, 2024) https://www.tampa.gov/news/2024-06/major-wastewater-project-completed-149691 Used for: flow diverted from Harbour Island force main, 78-inch pipeline, 13,700 feet, $83 million, PIPES program
  7. Tampa wastewater upgrade features major microtunnel project (ASCE Civil Engineering, September 21, 2023) https://www.asce.org/publications-and-news/civil-engineering-source/civil-engineering-magazine/article/2023/09/tampa-wastewater-upgrade-features-major-microtunnel-project Used for: 54-inch force main 1951, 11,134 linear feet, 2017 leaks under Harbour Island Bridge, Ybor Turning Basin crossing, April 2023 breakthrough
  8. Harbour Island residents seeking less invasive wastewater overhaul (Spectrum Bay News 9, May 16, 2018) https://baynews9.com/fl/tampa/news/2018/05/16/harbour-island-residents-seeking-less-invasive-wastewater-overhaul Used for: 2018 resident concerns over pipe route through island; pipes installed 1951
  9. Harbour Island wastewater project in full swing with new underground tunnel (FOX 13, August 16, 2023) https://www.fox13news.com/news/harbour-island-wastewater-project-in-full-swing-with-new-underground-tunnel Used for: $79 million cost figure, tunnel under Sparkman and Garrison channels, built to route around dense Harbour Island