Short answer: Vero Beach ran its own electric utility for nearly a century after taking over the private Vero Utilities Company plant in the early 1920s. Its Big Blue plant on 17th Street opened in 1961. High rates, about 58 percent above FPL in 2009, and a customer base mostly outside city limits led the city to sell Vero Electric to FPL for $185 million, a deal completed in December 2018.

How did Vero Beach end up owning an electric utility?

Vero Beach got into the power business by rescue rather than design. In a 2009 history of the system, Vero Beach 32963 reported that the city took over the first power plant built by the Vero Utilities Company in the early 1920s, when the private owners were unable to keep pace with growing customer demand. The Indian River Guardian, marking the end of local generation in 2015, put the purchase 96 years earlier and placed that first privately run plant downtown near the railroad tracks.

A larger diesel plant replaced it in the 1920s boom. When the City of Vero Beach was trying to resolve a failed redevelopment lease on the building in June 2013, Vero Beach 32963 described the vacant diesel power plant as an 87-year-old building, which dates it to 1926, and noted that one massive generator had been left inside as a showpiece of the early industrial history of Vero Beach.

Vero Beach was one of many Florida towns that kept a city utility. Florida Trend reported in March 2013 that Florida has 34 municipal electric utilities, that cities generally entered the business early in the twentieth century, some by taking over a failing private company, and that Vero Beach, at 34,000 customers, ranked 90th nationally among public power systems.

What was Big Blue, and how much power did it make?

The city moved generation to the Indian River in 1961. The first generating unit at the current 19.6-acre plant, located on the northeast corner of 17th Street and Indian River Boulevard, was put into commercial service in 1961, and Vero Beach 32963 listed four more: unit 2 in 1964, unit 3 in 1970, unit 4 in 1976 and unit 5 in 1992. Painted a distinctive aqua, the riverfront plant became known around Vero Beach as Big Blue.

By the 2000s Big Blue was a backup more than a source. In 2008, according to the same 2009 Vero Beach 32963 analysis, the plant could at best fill the needs of fewer than half the utility's 33,329 electric customers, and Vero Electric bought most of its power from the Florida Municipal Power Agency and later the Orlando Utilities Commission. Florida Trend reported in 2013 that Big Blue supplied only 1 percent of the city's load while it had to stay on call as a peaking plant.

Generation ended before the sale. On November 6, 2015, the Indian River Guardian reported, City Manager Jim O'Connor announced that the Orlando Utilities Commission would no longer call on the Vero Beach plant, leaving Vero Electric a distribution utility buying wholesale power. The paper reported that keeping the plant open and staffed had been costing the customers of Vero Electric some $4 million a year.

Why did Vero Beach decide to sell its electric system?

Rates and representation drove the push. The 2009 Vero Beach 32963 history found that about 61 percent of customers lived outside the city and only 39 percent inside, so most ratepayers could not vote for the Vero Beach City Council that set their rates. That summer Vero electric rates soared to 58 percent higher than FPL rates, Vero Beach 32963 later recalled, and profits from electric bills were helping fund the city's general budget.

The city formally opened talks in December 2009. Veronews reported in October 2011 that FPL representatives first visited the Vero Beach City Council in December 2009, when the council invited FPL to begin a conversation about a sale of the electric utility, and that FPL had been the only investor-owned utility to respond to the city's request for proposals. In November 2011, according to Vero Beach 32963, voters by a nearly 2-to-1 margin gave the council permission to lease the property under Big Blue as part of a sale.

How did the 2018 sale to FPL come together?

Contracts with the power agencies were the hard part. Vero Beach had to buy its way out of the Florida Municipal Power Agency co-op for $108 million and settle its Orlando Utilities Commission contract, according to Vero Beach 32963, and FPL raised its offer to $185 million for the system, enough to relieve Vero of its long-term contracts and leave $30 million to $40 million in cash. An FMPA release carried by the Indian River Guardian announced in February 2018 that the required 19 member cities had approved releasing Vero Beach from FMPA power projects.

State regulators then ruled. The FPL newsroom reported on June 5, 2018, that the Florida Public Service Commission approved the purchase of the City of Vero Beach electric utility after a nearly decade-long process, noting that the Vero Beach City Council had approved a $185 million agreement that allows the City to exit its contractual obligations, pay off its debt and receive a cash payment. FPL said its typical 1,000-kWh customer bill was about 20 percent lower than the City of Vero Beach bill. A PSC release stated that under the agreement FPL would purchase the Vero Beach utility system for $185 million by December 31, 2018.

The final steps came at the end of 2018. The Florida Municipal Electric Association, reposting the News Service of Florida, reported that the Public Service Commission gave final approvals on November 27, 2018, ended the territorial agreement that had divided Indian River County between the city utility and FPL, and let FPL charge its own rates to the former Vero Beach customers. At the December 2018 closing, Vero Beach 32963 reported, Big Blue became FPL territory at midnight and the city's bank account was $39 million richer.

What happened in Vero Beach after the electric sale?

The city budget had to adjust. Vero Beach 32963 reported in August 2022 that a glide path funded by sale proceeds was designed to wean Vero Beach off nearly $6 million in annual electric utility transfers to the general fund, that only $500,000 of that cushion remained, and that the city still held more than $21 million in sale cash set aside for redeveloping the riverfront power plant and sewer plant sites.

Big Blue itself stayed on the riverfront into the Three Corners planning. Veronews reported in November 2020 that city officials and the Three Corners Steering Committee were weighing whether to dismantle the 1961 plant or reuse it, and that the 10-year effort to sell Vero Electric had always included clearing the industrial site north of the 17th Street bridge. Electric service at Vero Beach homes and businesses has come from FPL since the December 2018 closing.

Frequently asked questions

When did Vero Beach start running its own electric utility?

In the early 1920s. Vero Beach 32963 reported that the city took over a plant built by the private Vero Utilities Company when its owners could not keep up with demand, and a 1926 diesel plant downtown followed.

What is Big Blue in Vero Beach?

Big Blue is the aqua power plant at 17th Street and Indian River Boulevard. Its first unit began commercial service in 1961, four more were added through 1992, and it stopped generating for the city in November 2015.

How much did FPL pay for Vero Electric?

The agreement was $185 million. After paying off debt and exiting its Florida Municipal Power Agency and Orlando Utilities Commission obligations, Vero Beach received a $39 million wire transfer at the December 2018 closing, according to Vero Beach 32963.

Why were customers outside Vero Beach unhappy with Vero Electric?

About 61 percent of customers lived outside the city in 2009 and could not vote for the City Council that set their rates, which that summer ran 58 percent above neighboring FPL rates.

Who approved the Vero Beach electric sale?

City voters approved related ballot questions, 19 FMPA member cities and the Orlando Utilities Commission signed off, federal regulators reviewed parts of the deal, and the Florida Public Service Commission approved it in 2018.

Sources

  1. Power plant not villain in soaring rates (Vero Beach 32963, August 13, 2009) https://vb32963online.com/STORIES 2009/AUGUST/vb63_powerplant_issue26_2009.html Used for: 1920s takeover, 1961 to 1992 units, plant location, customer count, outside-city split
  2. Diesel power plant, long vacant, soon may be up for sale (Vero Beach 32963, June 13, 2013) https://vb32963online.com/STORIES 2013/JUNE 2013/VB32963_Diesel_Power_Plant_May_Be_Up_For_Sale_Issue24_061313.html Used for: Age of the old diesel plant
  3. Power plant powered down (Indian River Guardian, November 7, 2015) https://indianriverguardian.com/2015/11/07/power-plant-powered-down/ Used for: End of generation, cost of keeping the plant, original downtown plant
  4. A surge in interest for Florida's municipal utilities (Florida Trend, March 4, 2013) https://www.floridatrend.com/article/15334/a-surge-in-interest Used for: Size ranking, 34 Florida municipal utilities, 1 percent of load
  5. Events focus on sale of Vero Beach Electric utility to FPL (Veronews, October 21, 2011) https://veronews.info/?p=56438 Used for: December 2009 invitation to FPL, 2011 referendum context
  6. Voters overwhelmingly approve leasing power plant site (Vero Beach 32963, November 10, 2011) https://vb32963online.com/STORIES 2011/NOVEMBER 2011/vb32963_voters_approve_referendum_issue45_111011.html Used for: November 2011 referendum result
  7. Vero to FPL: 'It's finally all yours' (Vero Beach 32963, December 2018) https://vb32963online.com/STORIES 2018/DECEMBER 2018/VB32963_Vero_To_FPL_Its_Finally_All_Yours_Issue51_122018.html Used for: Closing, $39 million transfer, 2009 rate gap, FMPA exit cost, deal terms
  8. All 19 FMPA cities approve Vero Beach transaction (Indian River Guardian, February 27, 2018, FMPA release) https://indianriverguardian.com/2018/02/27/all-19-fmpa-cities-approve-vero-beach-transaction/ Used for: FMPA member city approvals
  9. FPL receives final approval to purchase the City of Vero Beach electric system (FPL Newsroom, June 5, 2018) https://newsroom.fpl.com/2018-06-05-FPL-receives-final-approval-to-purchase-the-City-of-Vero-Beach-electric-system-and-welcome-35-000-new-customers-this-fall Used for: PSC approval, $185 million agreement, 35,000 customers, bill comparison, approvals list
  10. Florida Public Service Commission transfers Vero Beach Electric customers to FPL (Indian River Guardian, June 6, 2018, PSC release) https://indianriverguardian.com/2018/06/06/florida-public-service-commission-transfers-vero-beach-electric-customers-to-fpl/ Used for: PSC vote, rate decrease estimate, $185 million by December 31, 2018
  11. FPL Finishes Deal for Vero Beach Utility (FMEA, December 17, 2018) https://www.flpublicpower.com/news/fpl-finishes-deal-for-vero-beach-utility Used for: Completion, November 27 final approval, territorial agreement ended
  12. Big Blue's subsidy of Vero city budget is nearing an end (Vero Beach 32963, August 4, 2022) https://vb32963online.com/STORIES 2022/AUGUST 2022/VB32963_Big_Blues_Subsidy_Of_Vero_City_Budget_Is_Nearing_An_End_Issue31_080422.html Used for: General fund transfers and sale proceeds after the sale
  13. North of bridge, dismantle Big Blue or turn it into riverfront centerpiece? (Veronews, November 5, 2020) https://veronews.info/?p=141746 Used for: Big Blue after the sale
Last updated: October 8, 2026