The Compound — Palm Bay, Florida

Port Malabar Units 51, 52 and 53: thousands of General Development lots with roads and ditches but no pipes or power, and what Palm Bay plans next.


Short answer: The Compound is the nickname for Port Malabar Units 51, 52 and 53 in southwest Palm Bay: 4,978 mostly quarter-acre lots that General Development Corporation platted before going bankrupt in 1991. About 200 miles of roads were built, but the city says there is no water, sewer or electric service and the whole area lies in a flood zone. A Compound Redevelopment Action Plan published by the city in April 2025, prepared with EPA technical assistance, proposes a business park in Unit 53.

Last verified: October 13, 2026, against the sources listed at the end of this page.

What is the Compound in Palm Bay?

The Compound is the name for Port Malabar Units 51, 52 and 53, a mostly vacant block of pre-platted quarter-acre lots in southwest Palm Bay that General Development Corporation laid out but never built.

The City of Palm Bay describes the Compound as Port Malabar Units #51, 52 and 53, holding 4,978 parcels that are mostly quarter-acre single-family lots (City of Palm Bay, Compound Update). Those lots belong to 2,755 unique private property owners, a number the city says spans owners across the world. General Development Corporation (GDC) platted the land before the City of Palm Bay incorporated, which is why the street grid exists on paper and on the ground while almost nothing stands along it.

The nickname is local shorthand rather than a legal name. Palm Bay's own pages put it in quotation marks as the area referred to as the compound, and the EPA technical assistance team used the same label in its 2024 and 2025 reports. In the city's own map description the land is identified by its Port Malabar unit numbers, 51, 52 and 53.

What sets the Compound apart is the absence of everything beyond pavement and drainage. GDC left roughly 200 miles of roads plus stormwater ditches, outfalls, canals and headwalls, and the city states there is no existing water, sewer or electrical infrastructure within the Compound (Compound Update).

Where is the Compound and what borders it?

The Compound sits in the southwest corner of Palm Bay, bounded by Angora Street SW on the north, Alwar and Sage Avenues on the east, the Melbourne Tillman Canal on the south and the Three Forks Conservation Area on the west.

Those boundaries come from the EPA commercial market assessment dated March 28, 2025, which calls the Compound the Subject Site (Commercial Market Assessment, page 4). The same report places the Compound about 9 miles from I-95 (Commercial Market Assessment, page 4) and lists Melbourne Orlando Airport at 14 miles and Port Canaveral at 52 miles among the site's known assets (Commercial Market Assessment, page 6). The city's map of the Compound (Compound Update) shows an inset locating it in the southwest corner of the Palm Bay city limits, with an orange dashed line marking a proposed parkway running north to south through the center.

The EPA market assessment notes the Compound's adjacency to current industrial uses and says opportunities may exist for complementary land uses in the area owned by the City of Palm Bay (Commercial Market Assessment, page 6), and the EPA final webinar proposes a gateway at the Compound entrance along J.A. Bombardier (EPA final webinar, page 15). The East Central Florida Regional Planning Council (ECFRPC) singled out that corner as the northeast quadrant, citing large properties, contiguous ownership, proximity to BRP Inc., access to J.A. Bombardier and proximity to utilities (Strategic Plan Presentation, page 7). On the west side, the ECFRPC noted the Compound's proximity to the Three Forks Conservation Area and large parcels owned by the Melbourne Tillman Water Control District (Strategic Plan Presentation, page 8).

How big is the Compound, and why do the acreage figures differ?

Palm Bay documents give the Compound four different sizes, from about 2,300 to about 2,942 acres, because each one measures a different boundary or date, so each figure is quoted here with its own source.

Size of the Compound as stated in Palm Bay and EPA documents
DocumentTotal areaCity-owned land
City Compound Update, brownfields sectionabout 2,492 acresnot stated
City Compound Update, history sectionabout 2,942 acres278.4 acres
City Compound Update, map description2,784 acres235 acres
City Manager recruitment profile, 20252,942 acres278.4 acres, including the roads
EPA kickoff webinar, November 12, 2024approximately 2,300 acresnot stated

The single Compound Update page carries three of those numbers. Its brownfields paragraph says Port Malabar Units 51 to 53 span approximately 2,492 acres in southwest Palm Bay, its history paragraph calls the Compound an undeveloped area of approximately 2,942 acres, and its map description lists a total area of 2,784 acres with 235 acres city-owned (Compound Update). The history paragraph instead puts city ownership at 278.4 acres, several parcels of it being future right-of-way for roads, stormwater or future parks.

The 2025 City Manager recruitment profile repeats the larger figure, saying GDC dissolved in 1991, halting development in a 2,942-acre area of Palm Bay, with the City of Palm Bay owning 278.4 acres, including the roads (City of Palm Bay City Manager profile, page 6). The EPA kickoff webinar for the Compound, held November 12, 2024, describes the total site as approximately 2,300 acres with numerous owners, including the City of Palm Bay (EPA kickoff webinar, page 3). No Palm Bay document reconciles the figures.

Why did the Compound stay empty after General Development Corporation?

The Compound stalled when General Development Corporation went bankrupt in 1991, leaving thousands of separately owned lots with roads but no water, sewer or power and the whole area in a flood zone.

Palm Bay's history of the Compound says GDC development there began in the 1980s, and that when GDC went bankrupt in 1991 development stalled and the land was liquidated (Compound Update). The Compound today is mostly privately owned and zoned for residential use, while the City of Palm Bay owns the paved roadways. With over 2,700 owners besides the city, the Compound Update calls the scattered ownership a barrier for any organization trying to assemble large tracts of contiguous acres.

Cost is the second barrier. Water, sewer and electric lines would all have to be brought into the Compound, and the city notes the entire area is located in a flood zone. The ECFRPC's April 4, 2024 strategy presentation listed four physical problems specific to the Compound: the absence of a north to south connection, multiple ownership, a curvilinear street pattern and a small average lot size (Strategic Plan Presentation, page 5).

Palm Bay is not alone in this. The same ECFRPC deck pointed out that pre-platted communities are a problem found all over Florida, naming Cape Coral, Lehigh Acres and Murdock Village, and said no community has found ideal solutions (Strategic Plan Presentation, page 4). What differs in the Compound is scale and emptiness: the EPA kickoff notes that, unlike many pre-platted communities, it has very little residential intrusion (EPA kickoff webinar, page 3).

What has Palm Bay City Council planned for the Compound?

Palm Bay City Council adopted the ECFRPC's Compound Existing Land Use Analysis on April 4, 2024, and the city published a Compound Redevelopment Action Plan in April 2025, prepared with EPA technical assistance for a study focused on Port Malabar Unit 53.

The 2024 ECFRPC study sorted the Compound into zones. For the northeast corridor along J.A. Bombardier Boulevard SW it recommended land entitlement changes, city-initiated administrative rezoning, land acquisition, targeted infrastructure and using city land to recruit a firm to create and operate an industrial park (Strategic Plan Presentation, page 10). For the western Compound it recommended folding the westernmost segments into the Palm Bay Parks Master Plan and adopting a Transfer of Development Rights ordinance (Strategic Plan Presentation, page 11). For a future mixed-use and employment center it urged fast-tracking work with the Florida Department of Transportation and the Space Coast Transportation Planning Organization on the St. Johns Heritage Parkway, dedicating land for a future FPL substation and setting up a special assessment or community development district (Strategic Plan Presentation, page 12).

In November 2024 Palm Bay began a land revitalization study of Port Malabar Unit 53 funded through the EPA Land Use Revitalization Technical Assistance Program. The Compound Update states the EPA Region 4 assistance is valued at $100,000 with no city match, and that the work came from a nomination by the ECFRPC (Compound Update). Its planning next steps for Unit 53 include an area master plan, light manufacturing zoning, updated stormwater plans, reserved right-of-way for a future St. John Parkway corridor (the slide's wording) and Phase 1 environmental site assessments (EPA final webinar, page 13).

What would a business park in the Compound add up to?

The EPA team's concept for the northeast Compound is a four-phase business park of 960,000 square feet on about 86 acres, estimated at 2,500 direct jobs and $1,948,296 a year in Palm Bay property tax.

Business park phases in Port Malabar Unit 53 (EPA technical assistance, final webinar)
PhaseUseBuilding sq ftLand (about)Direct jobsAnnual city property tax
1Manufacturing, R&D, office380,00036 acres760$647,307
2R&D40,0003 acres180$202,690
3R&D120,00020 acres600$247,134
4Manufacturing, R&D, office420,00027 acres960$851,165
Total960,00086 acres2,500$1,948,296

The phase figures come from the final EPA technical assistance webinar, which puts total development cost at $300,128,000 against a value at completion of $286,224,000 (EPA final webinar, page 11). The same slide warns the Compound business park is a long-term play whose value at completion may be lower than cost, and that infrastructure costs will need to be absorbed elsewhere. Job and tax estimates exclude indirect benefits such as construction (EPA final webinar, page 12).

Infrastructure is the first step on the list: extend sewer and water into the northeast section of the Compound, commission engineering and cost estimates, prepare grant applications to the State of Florida and federal economic development programs, and coordinate with FPL on future energy needs and service (EPA final webinar, page 14). The marketing ideas include rebranding the land as Port Malabar Business Park with a gateway at the Compound entrance on J.A. Bombardier (EPA final webinar, page 15).

How does the brownfields grant apply to the Compound?

The Compound is the Palm Bay priority site in a $1.5 million EPA brownfields assessment grant, announced by the EPA in May 2024, that the East Central Florida Regional Planning Council received for a coalition it leads.

The City of Palm Bay's brownfields page says the grant is to be used community-wide over four years and is administered by the East Central Florida Resilient Corridors Coalition, which includes Palm Bay, south Melbourne, Kissimmee and Apopka (City of Palm Bay, Brownfields Grant). The money can pay for Phase I and Phase II environmental site assessments, which the city notes can be a cost barrier for development. At the start of 2025 Palm Bay planned a memorandum of understanding with the ECFRPC to formalize use of the funds in the Compound, with parcel identification and work with property owners among the grant deliverables listed on the Compound Update page.

Frequently asked questions

Why is it called the Compound?

The name is a local nickname for Port Malabar Units 51, 52 and 53. City of Palm Bay pages put it in quotation marks as the area referred to as the compound, while the city's map description identifies the area by its Port Malabar unit numbers, 51, 52 and 53.

Can a house be built on a lot in the Compound?

The land is zoned for residential use, but the City of Palm Bay says the Compound has no existing water, sewer or electrical infrastructure and lies entirely in a flood zone, and says water, sewer and electric lines would all have to be brought in, a cost barrier for building there.

Who owns the land in the Compound?

Mostly private owners. The city counts 2,755 unique private owners of 4,978 parcels. The City of Palm Bay owns the paved roads and scattered parcels, stated as 278.4 acres on one part of the Compound Update page and 235 acres on its map description.

Is the St. Johns Heritage Parkway planned through the Compound?

Palm Bay's map of the Compound shows a proposed parkway running north to south through its center, the EPA final webinar's next steps call for reserving right-of-way for a future St. John Parkway corridor, and the 2025 City Manager profile names the future extension of the St. Johns Heritage Parkway among the city's plans for the area. No construction date is given in those documents.

When could the Compound business park be built?

The EPA technical assistance documents for Port Malabar Unit 53 give no construction schedule. They list next steps first: an area master plan, rezoning for light manufacturing, utility extensions into the northeast Compound and grant applications, with either city-led recruitment or a master developer chosen by RFP.

Sources

  1. City of Palm Bay, Compound Update (Economic Development) https://www.palmbayfl.gov/government/city-departments-a-to-e/community-and-economic-development/economic-development/compound-update Used for: definition, Units 51 to 53, parcels, owners, acreage figures, GDC history, utilities, flood zone, EPA technical assistance, Existing Land Use Analysis adoption
  2. City of Palm Bay, Brownfields Grant https://www.palmbayfl.gov/government/city-departments-a-to-e/community-and-economic-development/economic-development/brownfields-grant Used for: $1.5 million ECFRPC brownfields assessment grant, coalition members, Phase I and II assessments
  3. ECFRPC and City of Palm Bay, The Compound Strategic Plan Presentation, April 4, 2024 (page 4) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=4 Used for: pre-platted communities statewide
  4. The Compound Strategic Plan Presentation (page 5) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=5 Used for: challenges
  5. The Compound Strategic Plan Presentation (page 7) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=7 Used for: northeast quadrant opportunity
  6. The Compound Strategic Plan Presentation (page 8) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=8 Used for: conservation opportunity, Three Forks, Melbourne Tillman Water Control District
  7. The Compound Strategic Plan Presentation (page 11) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=11 Used for: conservation recommendations, transfer of development rights
  8. The Compound Strategic Plan Presentation (page 12) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=12 Used for: mixed-use recommendations, FPL substation, special district
  9. EPA Region 4 Technical Assistance, The Compound, final webinar, Attachment 7 (page 11) https://www.palmbayfl.gov/home/showpublisheddocument/27880/638797062996870000#page=11 Used for: phase table
  10. EPA Region 4 Technical Assistance final webinar (page 12) https://www.palmbayfl.gov/home/showpublisheddocument/27880/638797062996870000#page=12 Used for: jobs and tax estimates
  11. EPA Region 4 Technical Assistance final webinar (page 13) https://www.palmbayfl.gov/home/showpublisheddocument/27880/638797062996870000#page=13 Used for: planning next steps
  12. EPA Region 4 Technical Assistance final webinar (page 14) https://www.palmbayfl.gov/home/showpublisheddocument/27880/638797062996870000#page=14 Used for: infrastructure next steps
  13. EPA Region 4 Technical Assistance final webinar (page 15) https://www.palmbayfl.gov/home/showpublisheddocument/27880/638797062996870000#page=15 Used for: marketing and redevelopment options
  14. Commercial Market Assessment, The Compound, March 28, 2025, Attachment 6 (page 4) https://www.palmbayfl.gov/home/showpublisheddocument/27878/638797062993430000#page=4 Used for: boundaries, distance to I-95
  15. Commercial Market Assessment, Attachment 6 (page 6) https://www.palmbayfl.gov/home/showpublisheddocument/27878/638797062993430000#page=6 Used for: distances to airport and Port Canaveral
  16. EPA Region 4 Technical Assistance kickoff webinar, November 12, 2024, Attachment 1 (page 3) https://www.palmbayfl.gov/home/showpublisheddocument/27868/638797062974170000#page=3 Used for: approximately 2,300 acres
  17. City of Palm Bay City Manager recruitment profile, 2025 (page 6) https://www.palmbayfl.gov/home/showpublisheddocument/27651/638717499109470000#page=6 Used for: 2,942 acres, 278.4 city-owned acres including roads
  18. ECFRPC and City of Palm Bay, The Compound Strategic Plan Presentation (page 10) https://www.palmbayfl.gov/home/showpublisheddocument/26962/638482696069200000#page=10 Used for: northeast corridor recommendations
Last updated: October 13, 2026