GO Roads Paving Program — Palm Bay, Florida

From the Unit 41 kickoff in 2019 to a 2025 pause at about 60% of 791 road miles, the Palm Bay road bond unit by unit.


Short answer: GO Roads is Palm Bay's street repaving program, funded by a $150 million general obligation bond that voters approved in November 2018. Paving began in 2019 in Unit 41, the city's fiscal 2024 financial report listed Phases 1 to 3 as complete, and about 60% of the city's 791 road miles had been resurfaced when the program paused in 2025, with a new citywide pavement condition survey planned. A street's phase is found by its unit number on the city GIS map.

Last verified: October 12, 2026, against the sources listed at the end of this page.

What is the Palm Bay GO Roads program?

GO Roads is Palm Bay's citywide street repaving program, paid for by a $150 million bond that Palm Bay voters approved in November 2018 and repaid from property taxes.

The ballot question was Referendum No. 2: Bonds for Road Improvement Projects in Palm Bay. Referendum No. 2 authorized the City of Palm Bay to issue GO bonds up to $150,000,000, repaid from annual property taxes. A general obligation bond is city debt backed by ad valorem taxes, which is why it needed a public vote, and the city called GO bonds the most cost-effective bonds to issue.

The Public Works Projects page lays out the original plan: five phases over an eight-year construction period, each one vetted by the Infrastructure Advisory and Oversight Board before going to Palm Bay City Council for final approval. Palm Bay officials held the kickoff event in Unit 41 on October 11, 2019, to mark the start of GO Roads paving.

The bond was never meant only for asphalt. The city's ballot glossary on the GO Bond page defines ancillary facilities as sidewalks and trails, streetlights and underground pipes related to the roadway, and Palm Bay Public Works schedules stormwater pipe replacement ahead of road bond paving (Public Works Projects).

The money was borrowed in pieces. Palm Bay's fiscal 2024 annual financial report says the GO Road Program Fund accounts for General Obligation Bonds, Series 2019, 2021 and 2023, and that at the end of fiscal 2024 the Palm Bay GO Road Program Fund still held $64.5 million in restricted net position.

How much of Palm Bay has GO Roads paved?

By October 27, 2025, Palm Bay Public Works reported that GO Roads had resurfaced about 60% of the 791 miles of Palm Bay roadway, up from 51% in February 2024.

GO Roads progress in Palm Bay as reported by the city
DateMiles or share pavedSource
Fiscal 2023 report355 miles, 45%FY 2023 annual financial report
February 2024403 miles, 51% of 791FY 2023 annual financial report
September 2024440 miles, 56% of 791FY 2024 annual financial report
Undated status noteover 418 milesPublic Works Projects page
October 27, 2025about 60% of 791IAOB minutes

The city's fiscal 2023 report counted 403 miles or 51% as of February 2024, and its fiscal 2024 report counted 440 miles or 56% of the 791 miles of roadway as of September 2024. The Infrastructure Advisory and Oversight Board minutes of October 27, 2025 put the total at about 60% of the 791 miles of Palm Bay roadway. The Public Works Projects page still shows an undated figure of over 418 miles, which falls between the two 2024 counts, so each number is given here with its own date.

Phase by phase, the fiscal 2024 report says Palm Bay Public Works had completed all of Phases 1, 2 and 3, with Phase 4 projects headed to bid in fiscal 2025. Note 7 of the fiscal 2023 report lists the GO Bond Road Program with $88,564,331 spent to date and $61,435,669 of remaining commitment at September 30, 2023.

Which Palm Bay neighborhoods were paved in Phases 1 to 3?

The first three GO Roads phases covered areas from Unit 41 and Garvey Road to Port Malabar Boulevard, Palm Bay Colony and the Country Club units.

Selected completed GO Roads projects in Palm Bay (Public Works Projects page, read October 12, 2026)
AreaPhaseMilesCost
Unit 41 and Eldron111.21$3,074,559
Units 31 and 32141.47$10,269,206
Unit 42 and Garvey Road133.51$7,727,462
Units 11, 15, 18, 23 and 56156.63$10,020,962
Units 24 and 25245.37$7,861,369
Country Club Units 1 to 10 (Port Malabar)220.90$8,894,381
Unit 30330.10$11,923,113
Units 13, 14, Madden and Osmosis334.16$11,139,620
Waco and Minton32.39$2,834,000

The Public Works unit table also lists Phase 2 work on Port Malabar Road from Palm Bay Road to Babcock Street, Emerson Drive from Minton Road to C-1, Palm Bay Colony and Kirby Industrial, Driskell Heights, Knecht Road, and Port Malabar from Babcock Street to U.S. 1. One unit number differs between city pages: the GO Bond page gives Unit 41 and Eldron as 11.73 miles, against 11.21 on the projects table.

Major roads were added along the way. In July 2024 Palm Bay City Council approved $4,000,000 in GO Road funds to pave Emerson Drive from Malabar Road to Waco Boulevard (Council minutes, July 18, 2024), and in June 2022 the Unit 30 contract went to a Vero Beach paving contractor for $11,625,262 (Council minutes, June 16, 2022).

How can a Palm Bay street be matched to its unit and phase?

The city's GIS map shows a Palm Bay residence's unit as a yellow filled number, which can then be matched to the GO Roads phase tables.

Palm Bay Public Works lists most GO Roads paving by unit rather than by street name. The Public Works Projects page tells residents to search an address on the city GIS map and look for the yellow filled number to identify the unit, then read the phase table and the color-coded phase map below it.

The remaining units are listed on the GO Bond page. Phase 4 groups Units 6, 44, 45, 50 and 55, about 96.7 miles at an estimated $13,838,501. Phase 5 covers Units 26, 38, 39 and 40 (19.39 miles); Melbourne Poultry Colony and Units 21, 7, 8, 29, 28, 19, 10, 9, 36, 12 and 16 (223.71 miles, estimated at $37,673,563); and Unit 49 (28.4 miles at $16,153,422).

Those lists were already shifting in 2025. At the April 28, 2025 board meeting the city said the City of Palm Bay had allocated funds for the first four of the five phases and Phase 5 was not funded, with Phase 4 contracts soon to be awarded for Units 22, 37, 57, 26 and 39 cul-de-sacs and bids planned for Units 44, 45, 50 and 55. The five-year capital plan for fiscal 2025 to 2029 nonetheless scheduled $27,268,338 in GO Road Bond paving for fiscal year 2026: Units 29, 36 and 49, Malabar Road from C-10 to I-95, Jupiter Road from Garvey to San Filippo, and Melbourne Poultry Colony.

GO Road Bond paving scheduled for FY 2026 in Palm Bay's FY 2025-2029 CIP
ProjectFY 2026 amount
Unit 29 road paving$1,596,672
Unit 36 road paving$5,658,206
Malabar Road, C-10 to I-95$6,818,918
Jupiter Road, Garvey to San Filippo$1,142,718
Melbourne Poultry Colony$1,030,352
Unit 49 road paving$11,021,472
Total$27,268,338

Why did Palm Bay pause GO Roads in 2025?

Palm Bay paused GO Roads in 2025 after City Council voted to suspend future paving contracts, and staff planned a new citywide pavement condition survey to guide how the remaining bond money is spent.

The suspension surfaced at the September 22, 2025 Infrastructure Advisory and Oversight Board meeting, where the chair reported that Palm Bay City Council had voted to suspend any future GO Roads paving contracts. The chair sought board consensus to recommend a Pavement Condition Index before any future contracts; he put the cost between $150,000 and $200,000, not paid from bond money, and the Public Works Director said the new survey would be compared with the last one, done in 2017.

A month later the director gave the board the full history. The October 27, 2025 minutes record that the GO Roads program began in 2017 with a Pavement Management Plan by Trans Map, paving began in 2019 and the program paused in 2025. Trans Map had scored every Palm Bay road segment from 0 to 100 after driving it with video and infrared equipment.

The plan going forward is data first. Per the same minutes, the new condition scores will be combined with traffic study data to decide the best use of the remaining funds, and Palm Bay Public Works expected to have a project ready in the first quarter of 2026. For Palm Bay units not yet paved, the Phase 4 and Phase 5 rows on the GO Bond page are labeled estimates, not a schedule.

GO Roads bond cost and paving methods in Palm Bay

Palm Bay owners repay GO Roads through a separate debt millage on the property tax bill, and the program uses five treatments from rejuvenation to full reconstruction depending on how worn a street is.

For the first $50 million issue, the GO Bond page showed an estimated millage rate of 0.8296, about $82.96 a year on $100,000 of taxable value non-school, first billed in November 2019, with the note that the amount would rise as more bonds were issued. The charge follows taxable value, so exemptions lower it and wholly exempt institutions pay nothing; the separate Palm Bay stormwater assessment is not replaced by it.

Palm Bay Public Works chooses the treatment street by street (Public Works Projects). Mill and pave grinds off the old surface and lays 1.5 or 2 inches of new asphalt. Thin lift repairs cracks and potholes and adds a 1.5-inch overlay. Full depth reclamation pulverizes the old asphalt and base, mixes in cement, emulsion and water, and compacts it into a new base before paving. Full reconstruction removes the road down to subgrade and rebuilds it with an 8-inch base and 2 inches of asphalt.

Rejuvenation is the maintenance step for Palm Bay streets paved in the last few years: the GO Bond page says the Reclamite treatment on 1 to 5 year old roads improves the durability and life of the pavement by 4 to 6 years. Spending is watched by the Infrastructure Advisory and Oversight Board, which meets at Palm Bay City Hall, 120 Malabar Road SE.

Last verified: October 12, 2026, on the City of Palm Bay Public Works GO Roads pages and board minutes.

Frequently asked questions

How much was the Palm Bay GO Roads bond?

Palm Bay voters approved Referendum No. 2 in November 2018, authorizing up to $150,000,000 in general obligation bonds for road improvements, repaid from property taxes. The city issued the bonds in Series 2019, 2021 and 2023, according to its fiscal 2024 annual financial report.

Is GO Roads paving still happening in Palm Bay?

Palm Bay City Council voted in 2025 to suspend future GO Roads paving contracts, as reported to the Infrastructure Advisory and Oversight Board on September 22, 2025. Staff planned a new Pavement Condition Index and expected a project ready in the first quarter of 2026.

How is a Palm Bay neighborhood's GO Roads phase found?

Palm Bay Public Works directs residents to the city GIS map: searching an address shows a yellow filled number, which is the unit. That unit number is then matched to the phase tables and phase map on the Public Works GO Roads pages.

Does the GO Roads bond cover sidewalks in Palm Bay?

The ballot glossary on the Palm Bay GO Bond page counts sidewalks and trails, streetlights and roadway pipes as ancillary facilities the bond may fund. The Public Works Projects page says stormwater pipe replacement is done ahead of road bond paving.

What did GO Roads cost a Palm Bay homeowner?

For the first $50 million issue, the city estimated 0.8296 mills, about $82.96 a year per $100,000 of taxable value non-school, starting with November 2019 tax bills. The city said the levy would rise as later bond series were issued.

Sources

  1. City of Palm Bay Public Works, Projects page (GO Road Bond Improvement Projects) https://www.palmbayfl.gov/government/city-departments-f-to-z/public-works/projects Used for: bond, phases, kickoff, 418 miles, unit table, paving methods, Phase 5 unfunded, GIS unit lookup
  2. City of Palm Bay, GO Bond for Road Improvement Projects in Palm Bay (FAQ and phase tables) https://www.palmbayfl.gov/government/city-departments-f-to-z/public-works/projects/go-bond-for-road-improvement-projects-in-palm-bay Used for: Referendum No. 2, $150,000,000 cap, Phase One millage estimate, ballot terms, oversight, Phase 4 and 5 lists, rejuvenation
  3. Palm Bay Infrastructure Advisory and Oversight Board minutes, October 27, 2025, page 1 https://www.palmbayfl.gov/home/showpublisheddocument/28631/639039797482430000#page=1 Used for: program start 2017, paving 2019, pause 2025, Trans Map PCI
  4. Palm Bay IAOB minutes, October 27, 2025, page 2 https://www.palmbayfl.gov/home/showpublisheddocument/28631/639039797482430000#page=2 Used for: about 60% of 791 miles resurfaced, project expected first quarter 2026
  5. Palm Bay IAOB minutes, September 22, 2025, page 2 https://www.palmbayfl.gov/home/showpublisheddocument/28458/638962211379570000#page=2 Used for: City Council voted to suspend future GO Roads contracts
  6. Palm Bay IAOB minutes, September 22, 2025, page 3 https://www.palmbayfl.gov/home/showpublisheddocument/28458/638962211379570000#page=3 Used for: PCI cost $150,000 to $200,000 not from bond monies; last PCI 2017
  7. Palm Bay IAOB minutes, April 28, 2025, page 2 https://www.palmbayfl.gov/home/showpublisheddocument/28061#page=2 Used for: funds allocated for four of five phases, Phase 4 unit contracts and bids
  8. City of Palm Bay Annual Comprehensive Financial Report FY 2024, transmittal letter page 10 https://www.palmbayfl.gov/home/showpublisheddocument/28053/638844550492030000#page=10 Used for: 440 miles or 56% of 791 miles as of September 2024
  9. City of Palm Bay ACFR FY 2024, page 16 https://www.palmbayfl.gov/home/showpublisheddocument/28053/638844550492030000#page=16 Used for: Phases 1, 2 and 3 complete; Phase 4 to bid in FY 25
  10. City of Palm Bay ACFR FY 2024, page 38 https://www.palmbayfl.gov/home/showpublisheddocument/28053/638844550492030000#page=38 Used for: GO Road Program Fund, Series 2019, 2021 and 2023 bonds, $64.5 million restricted net position
  11. City of Palm Bay ACFR FY 2023, page 10 https://www.palmbayfl.gov/home/showpublisheddocument/27177/638576033787270000#page=10 Used for: 403 miles or 51% as of February 2024
  12. City of Palm Bay ACFR FY 2023, page 15 https://www.palmbayfl.gov/home/showpublisheddocument/27177/638576033787270000#page=15 Used for: phase completion percentages
  13. City of Palm Bay ACFR FY 2023, Note 7 construction commitments, page 91 https://www.palmbayfl.gov/home/showpublisheddocument/27177/638576033787270000#page=91 Used for: GO Bond Road Program spent to date and remaining commitment
  14. City of Palm Bay Five-Year CIP FY 2025-2029, page 7 https://www.palmbayfl.gov/home/showpublisheddocument/27582/638670100220970000#page=7 Used for: FY 2026 GO Road Bond paving projects and total
  15. Palm Bay City Council minutes, July 18, 2024, page 16 https://www.palmbayfl.gov/home/showpublisheddocument/27342/638621622071400000#page=16 Used for: $4,000,000 GO Road funds for Emerson Drive, Malabar Road to Waco Boulevard
  16. Palm Bay City Council minutes, June 16, 2022, page 12 https://www.palmbayfl.gov/home/showpublisheddocument/25589/637940848234930000#page=12 Used for: Unit 30 road bond paving award
Last updated: October 12, 2026